Skip to main content
← Back

Sai Chambers, Shivajinagar

Finishing stage

Final finishes 92% · completion not yet filed on MahaRERA

by Milind Ramkrishna Upasani. Shivajinagar, Pune 411005. View on Google Maps

Launched
1 year 5 months originally promised
Possession date (MahaRERA)
4 years 10 months ago. No further extension recordedExtended by 2 years 11 months (originally January 2019). Why possession dates change
Concrete structure (RCC)
95%Finishing stage
Units booked
13 of 6520% booked

Project facts

1 RK1
Other units (shops, offices or not given by type)64
Total units65
Buildings1
Land0.2 acres
Landowner share10
Complaints on MahaRERA (filed by or against the builder)1

Since Dec 2025: final finishes 91% → 92%

Share on WhatsApp

Construction progress

As reported to MahaRERA at each update
Time used and structure built
All of the originally promised 1 year 5 months have passed
Concrete structure (RCC) 95% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 100%Jun 2024: Excavation 100%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 80%Jun 2024: Concrete structure (RCC) 95%Dec 2024: Concrete structure (RCC) 95%Jun 2025: Concrete structure (RCC) 95%Dec 2025: Concrete structure (RCC) 95%Jul 2026: Concrete structure (RCC) 95%Dec 2023: Final finishes 75%Jun 2024: Final finishes 60%Dec 2024: Final finishes 60%Jun 2025: Final finishes 60%Dec 2025: Final finishes 91%Jul 2026: Final finishes 92%Excavation 100%Concrete structure (RCC) 95%Final finishes 92%

If a percentage drops between updates, we show it as MahaRERA reported it.

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%95%92%13
100%95%91%13
100%95%60%8
100%80%75%18

"—" means MahaRERA shows no figure for that update.

About this project

Sai Chambers (MahaRERA P52100010639) is a residential project by Milind Ramkrishna Upasani in Shivajinagar, Pune 411005. It was launched in August 2017. It has 65 units in 1 building: 1 home (1 RK) and 64 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Possession was due in December 2021, after an extension of 2 years 11 months from the original January 2019. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 95% complete, final finishes 92% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.

13 of its 65 units are booked (20%).

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100010639.Check it on MahaRERA (P52100010639)All projects in Shivajinagar