Vaishnavi Vihar, Ambegaon Budruk
Lapsed
by Vaishnavi Constructions. Ambegaon Budruk, Pune 411046. View on Google Maps
- Launched
- 3 years 10 months originally promised
- Possession date (MahaRERA)
- 4 years 4 months ago. No further extension recordedExtended by 1 year (originally June 2021). What "Lapsed" means
- Concrete structure (RCC)
- 100%Nearing possessionAverage across 2 buildings
- Units booked
- 36 of 5664% booked
Project facts
| 1 BHK | 21 |
|---|---|
| 2 BHK | 19 |
| Other units (shops, offices or not given by type) | 16 |
| Total units | 56 |
| Buildings | 2 |
| Land | 0.6 acres |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Since Dec 2025: booked 29 → 36
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 50% | 36 | |
| 100% | 100% | 50% | 29 |
"—" means MahaRERA shows no figure for that update.
About this project
Vaishnavi Vihar (MahaRERA P52100011466) is a residential project by Vaishnavi Constructions in Ambegaon Budruk, Pune 411046. It was launched in August 2017. It has 56 units in 2 buildings: 40 homes (1 & 2 BHK) and 16 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in June 2022, after an extension of 1 year from the original June 2021. That date has passed and no further extension has been recorded. Construction, averaged across its 2 buildings: excavation complete, structure (RCC) complete, final finishes 50% complete. MahaRERA records do not show it as ready to move in.
36 of its 56 units are booked (64%). Since the December 2025 update, 7 more units have been booked.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.