Skip to main content
← Back

Creative Ventures Chakan

by Creative Ventures Chakan. Chakan, Pune 410501. View on Google Maps

Launched
4 years 3 months originally promised
Possession date (MahaRERA)
4 years 4 months ago. No further extension recordedExtended by 6 months (originally December 2021). Why possession dates change
Concrete structure (RCC)
50%Mid-constructionAverage across 2 buildings
Units booked
9 of 4221% booked

Project facts

Other units (shops, offices or not given by type)42
Total units42
Buildings2
Land0.3 acres
Complaints on MahaRERA (filed by or against the builder)0
Share on WhatsApp

Construction progress

As reported to MahaRERA at each update
Time used and structure built
All of the originally promised 4 years 3 months have passed
Concrete structure (RCC) 50% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 100%Jun 2024: Excavation 100%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 50%Jun 2024: Concrete structure (RCC) 50%Dec 2024: Concrete structure (RCC) 50%Jun 2025: Concrete structure (RCC) 50%Dec 2025: Concrete structure (RCC) 50%Jul 2026: Concrete structure (RCC) 50%Dec 2023: Final finishes 45%Jun 2024: Final finishes 45%Dec 2024: Final finishes 45%Jun 2025: Final finishes 45%Dec 2025: Final finishes 45%Jul 2026: Final finishes 45%Excavation 100%Concrete structure (RCC) 50%Final finishes 45%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%50%45%9

"—" means MahaRERA shows no figure for that update.

About this project

Creative Ventures Chakan (MahaRERA P52100013192) is a residential project by Creative Ventures Chakan in Chakan, Pune 410501. It was launched in September 2017. It has 42 units, as registered with MahaRERA. Its MahaRERA status is Active.

Possession was due in June 2022, after an extension of 6 months from the original December 2021. That date has passed and no further extension has been recorded. Construction, averaged across its 2 buildings: excavation complete, structure (RCC) 50% complete, final finishes 45% complete. MahaRERA records do not show it as ready to move in.

9 of its 42 units are booked (21%).

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100013192.Check it on MahaRERA (P52100013192)All projects in Chakan