Skip to main content
← Back

Mount Brisa - Phase I, Yewalewadi

by Siddhant Realties. Yewalewadi, Pune 411048. View on Google Maps

Launched
5 years 3 months originally promised
Possession date (MahaRERA)
2 years 2 months awayExtended by 6 years (originally December 2022). Why possession dates change
Concrete structure (RCC)
72%Mid-construction
Units booked
56 of 13841% booked

Project facts

1 BHK62
2 BHK58
Other units (shops, offices or not given by type)18
Total units138
Buildings1
Land2.8 acres
Landowner share45
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: booked 47 → 56

Share on WhatsApp

Construction progress

As reported to MahaRERA at each update
Time used and structure built
All of the originally promised 5 years 3 months have passed
Concrete structure (RCC) 72% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 100%Jun 2024: Excavation 100%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 100%Jun 2024: Concrete structure (RCC) 72%Dec 2024: Concrete structure (RCC) 72%Jun 2025: Concrete structure (RCC) 72%Dec 2025: Concrete structure (RCC) 72%Jul 2026: Concrete structure (RCC) 72%Dec 2023: Final finishes 100%Jun 2024: Final finishes 72%Dec 2024: Final finishes 72%Jun 2025: Final finishes 72%Dec 2025: Final finishes 72%Jul 2026: Final finishes 72%Excavation 100%Concrete structure (RCC) 72%Final finishes 72%

If a percentage drops between updates, we show it as MahaRERA reported it.

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%72%72%56
100%72%72%47
100%100%100%54

"—" means MahaRERA shows no figure for that update.

Other phases of this project

About this project

Mount Brisa - Phase I (MahaRERA P52100013259) is a residential project by Siddhant Realties in Yewalewadi, Pune 411048. It was launched in September 2017. It has 138 units in 1 building: 120 homes (1 & 2 BHK) and 18 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2028, extended by 6 years from the original December 2022. Construction: excavation complete, structure (RCC) 72% complete, final finishes 72% complete. MahaRERA records do not show it as ready to move in.

56 of its 138 units are booked (41%). Since the December 2025 update, 9 more units have been booked.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100013259.Check it on MahaRERA (P52100013259)All projects in Kondhwa, Yewalewadi, Pisoli