Mount Brisa, Yewalewadi
by Siddhant Realties. Yewalewadi, Pune 411048. View on Google Maps
- Launched
- First of 2 phases
- Possession dates (MahaRERA)
- Dec 20282 of 2 phases have an extended possession date. Reading a project's possession date
- Concrete structure (RCC)
- 84%Mid-construction0 of 2 phases with structure completeWeighted across 2 phases
- Units booked
- 98 of 19750% booked
Facts
Project facts
| 1 BHK | 208 |
|---|---|
| 2 BHK | 88 |
| Total units | 325 |
| Buildings | 4 |
| Land | 2.8 acres |
| Phases | 2 |
Since Dec 2025: booked 77 → 98
Shortlist 2 or more to compare side by side.
Phases
The 2 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| Mount Brisa - Phase I Mid-construction | P52100013259 | 120 | 72% | 41% | |
| Mount Brisa Phase II Mid-construction | P52100018901 | 176 | 93% | 22% |
Show updates by phase
Mount Brisa - Phase I (P52100013259)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 72% | 72% | 56 | |
| 100% | 72% | 72% | 47 | |
| 100% | 100% | 100% | 54 |
"—" means MahaRERA shows no figure for that update.
Mount Brisa Phase II (P52100018901)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 93% | 33% | 42 | |
| 100% | 93% | 33% | 30 | |
| 100% | 69% | 33% | 30 | |
| 93% | 47% | 33% | 30 | |
| 67% | 37% | 33% | 19 |
"—" means MahaRERA shows no figure for that update.
Compare
Compared with 3 similar projects in PIN 411048
Projects with 100–600 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 5 yrs 2 mths | 6 yrs 6 mths |
| Possession date extended | Yes | 2 of 3 |
| Possession date (MahaRERA) | Dec 2028 | December 2025 |
| Concrete structure (RCC) | 84% | 45% |
| Units booked | 50% | 36% |
| MahaRERA complaints (filed by or against the builder) | 0 | 3 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Nobles Heights Building A1 AND A2-Phase 1 | August 2017 | January 2025 | 45% | 108 of 160 booked (68%) |
| The Latitude | July 2017 | Dec 2026 – Dec 2029 | 8% | 1 of 22 booked (5%) |
| Sky Gardens | June 2018 | December 2025 | 95% | 59 of 165 booked (36%) |
How to read construction stages
- Early stage
- The concrete structure (RCC) has not started yet.
- Mid-construction
- The concrete structure (RCC) is being built.
- Nearing possession
- The concrete structure (RCC) is complete and final finishes are below 90%.
- Ready to move
- MahaRERA shows the project Completed, or the concrete structure (RCC) is complete and final finishes are 90% or more.
- Concrete structure (RCC)
- The reinforced-concrete frame of the building: columns, beams and slabs.
- Final finishes
- Lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- Lapsed
- MahaRERA status when the possession date has passed with no extension or completion filed; it does not by itself mean work has stopped.
About this project
Mount Brisa is a project by Siddhant Realties in Yewalewadi, Pune 411048, registered with MahaRERA as 2 phases (P52100013259, P52100018901). The first phase was launched in September 2017. Together the phases have 325 units in 4 buildings, with 1 & 2 BHK homes as registered with MahaRERA. All 2 phases are active on MahaRERA.
The registered possession date is December 2028; 2 of 2 phases have an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 84% complete and final finishes 49% complete. 0 of the 2 phases have their structure complete.
98 of the 197 units reported for sale are booked (50%).