Mount Brisa, Yewalewadi

by Siddhant Realties. Yewalewadi, Pune 411048. View on Google Maps

Launched
First of 2 phases
Possession dates (MahaRERA)
Dec 20282 of 2 phases have an extended possession date. Reading a project's possession date
Concrete structure (RCC)
84%Mid-construction0 of 2 phases with structure completeWeighted across 2 phases
Units booked
98 of 19750% booked

Project facts

1 BHK208
2 BHK88
Total units325
Buildings4
Land2.8 acres
Phases2

Since Dec 2025: booked 77 → 98

Share on WhatsApp

Shortlist 2 or more to compare side by side.

The 2 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Mount Brisa - Phase I
Mid-construction
P5210001325912072%41%
Mount Brisa Phase II
Mid-construction
P5210001890117693%22%
Show updates by phase

Mount Brisa - Phase I (P52100013259)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%72%72%56
100%72%72%47
100%100%100%54

"—" means MahaRERA shows no figure for that update.

Mount Brisa Phase II (P52100018901)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%93%33%42
100%93%33%30
100%69%33%30
93%47%33%30
67%37%33%19

"—" means MahaRERA shows no figure for that update.

Compared with 3 similar projects in PIN 411048

Projects with 100–600 flats, launched within 1 year of this one.

Compared with 3 similar projects in PIN 411048
MeasureThis projectSimilar projects
Promised timeline (launch to possession)5 yrs 2 mths6 yrs 6 mths
Possession date extendedYes2 of 3
Possession date (MahaRERA)Dec 2028December 2025
Concrete structure (RCC)84%45%
Units booked50%36%
MahaRERA complaints (filed by or against the builder)03

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

How to read construction stages
Early stage
The concrete structure (RCC) has not started yet.
Mid-construction
The concrete structure (RCC) is being built.
Nearing possession
The concrete structure (RCC) is complete and final finishes are below 90%.
Ready to move
MahaRERA shows the project Completed, or the concrete structure (RCC) is complete and final finishes are 90% or more.
Concrete structure (RCC)
The reinforced-concrete frame of the building: columns, beams and slabs.
Final finishes
Lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
Lapsed
MahaRERA status when the possession date has passed with no extension or completion filed; it does not by itself mean work has stopped.

How to read construction stages

About this project

Mount Brisa is a project by Siddhant Realties in Yewalewadi, Pune 411048, registered with MahaRERA as 2 phases (P52100013259, P52100018901). The first phase was launched in September 2017. Together the phases have 325 units in 4 buildings, with 1 & 2 BHK homes as registered with MahaRERA. All 2 phases are active on MahaRERA.

The registered possession date is December 2028; 2 of 2 phases have an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 84% complete and final finishes 49% complete. 0 of the 2 phases have their structure complete.

98 of the 197 units reported for sale are booked (50%).

Source: MahaRERA registrations P52100013259 and P52100018901.Open MahaRERA and search P52100013259All projects in Kondhwa, Yewalewadi, Pisoli