Skip to main content
← Back

Arcadia, Bhilarewadi

Lapsed

by Acme Sawant Ventures. Bhilarewadi, Pune 411046. View on Google Maps

Launched
5 years 2 months originally promised
Possession date (MahaRERA)
2 years 10 months ago. No further extension recordedExtended by 1 year (originally December 2022). What "Lapsed" means
Concrete structure (RCC)
50%Mid-constructionAverage across 2 buildings
Units booked
70 of 11959% booked

Project facts

1 BHK79
2 BHK27
4 BHK1
Other units (shops, offices or not given by type)12
Total units119
Buildings2
Land1.3 acres
Landowner share41
Complaints on MahaRERA (filed by or against the builder)2

Since Dec 2025: booked 69 → 70

Share on WhatsApp

Construction progress

As reported to MahaRERA at each update
Time used and structure built
All of the originally promised 5 years 2 months have passed
Concrete structure (RCC) 50% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 50%Jun 2024: Excavation 50%Dec 2024: Excavation 50%Jun 2025: Excavation 50%Dec 2025: Excavation 50%Jul 2026: Excavation 50%Dec 2023: Concrete structure (RCC) 50%Jun 2024: Concrete structure (RCC) 50%Dec 2024: Concrete structure (RCC) 50%Jun 2025: Concrete structure (RCC) 50%Dec 2025: Concrete structure (RCC) 50%Jul 2026: Concrete structure (RCC) 50%Dec 2023: Final finishes 49%Jun 2024: Final finishes 49%Dec 2024: Final finishes 49%Jun 2025: Final finishes 49%Dec 2025: Final finishes 50%Jul 2026: Final finishes 50%Excavation 50%Concrete structure (RCC) 50%Final finishes 50%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
50%50%50%70
50%50%50%69
50%50%49%106
50%50%49%50

"—" means MahaRERA shows no figure for that update.

About this project

Arcadia (MahaRERA P52100013508) is a residential project by Acme Sawant Ventures in Bhilarewadi, Pune 411046. It was launched in October 2017. It has 119 units in 2 buildings: 107 homes (1, 2 & 4 BHK) and 12 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2023, after an extension of 1 year from the original December 2022. That date has passed and no further extension has been recorded. Construction, averaged across its 2 buildings: excavation 50% complete, structure (RCC) 50% complete, final finishes 50% complete. MahaRERA records do not show it as ready to move in.

70 of its 119 units are booked (59%). Since the December 2025 update, 1 more unit has been booked.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100013508.Check it on MahaRERA (P52100013508)All projects in Ambegaon, Katraj