Siddhi Vihar Wing A, Hadapsar
Finishing stage
Final finishes 100% · completion not yet filed on MahaRERA
by Bhosaletupe Dvelopers. Hadapsar, Pune 411028. View on Google Maps
- Launched
- 2 years 1 month originally promised
- Possession date (MahaRERA)
- 2 years 1 month ago. No further extension recordedExtended by 4 years 9 months (originally December 2019). Why possession dates change
- Concrete structure (RCC)
- 100%Finishing stage
- Units booked
- 13 of 7218% booked
Project facts
| 1 BHK | 45 |
|---|---|
| Other units (shops, offices or not given by type) | 27 |
| Total units | 72 |
| Buildings | 1 |
| Land | 0.5 acres |
| Reserved units | 17 |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 13 | |
| 100% | 100% | 100% | 29 |
"—" means MahaRERA shows no figure for that update.
About this project
Siddhi Vihar Wing A (MahaRERA P52100014026) is a residential project by Bhosaletupe Dvelopers in Hadapsar, Pune 411028. It was launched in November 2017. It has 72 units in 1 building: 45 homes (1 BHK) and 27 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Possession was due in September 2024, after an extension of 4 years 9 months from the original December 2019. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete (structure and final finishes), but completion has not yet been recorded on MahaRERA.
13 of its 72 units are booked (18%).
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.