Skip to main content
← Back

Srushti Apartment, Tathawade

Lapsed

by Rachana Creaters. Tathawade, Pune 411033. View on Google Maps

Launched
1 year 11 months originally promised
Possession date (MahaRERA)
6 years 9 months ago. No further extension recordedExtended by 3 months (originally October 2019). What "Lapsed" means
Concrete structure (RCC)
100%Nearing possession
Units booked
13 of 1681% booked

Project facts

1 BHK16
Total units16
Buildings1
Land0.2 acres
Landowner share3
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: booked 4 → 13

Share on WhatsApp

Construction progress

As reported to MahaRERA at each update
Time used and structure built
All of the originally promised 1 year 11 months have passed
Concrete structure (RCC) 100% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Jun 2024: Excavation 100%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Jun 2024: Concrete structure (RCC) 100%Dec 2024: Concrete structure (RCC) 100%Jun 2025: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 100%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%0%13
100%100%0%4

"—" means MahaRERA shows no figure for that update.

About this project

Srushti Apartment (MahaRERA P52100014366) is a residential project by Rachana Creaters in Tathawade, Pune 411033. It was launched in November 2017. It has 16 units in 1 building, with 1 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in January 2020, after an extension of 3 months from the original October 2019. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes not started. MahaRERA records do not show it as ready to move in.

13 of its 16 units are booked (81%). Since the December 2025 update, 9 more units have been booked.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100014366.Check it on MahaRERA (P52100014366)All projects in Tathawade, Punawale, Jambhe