The Luxe Towers - Building I and J, Senapati Bapat Road
Finishing stage
Final finishes 95% · completion not yet filed on MahaRERA
by Neelsidhi Mohar Raisoni Developers LLP. Senapati Bapat Road, Pune 411016. View on Google Maps
- Launched
- 4 years 9 months originally promised
- Possession date (MahaRERA)
- 1 year 2 months awayExtended by 5 years (originally December 2022). Why possession dates change
- Concrete structure (RCC)
- 100%Finishing stageAverage across 3 buildings
- Units booked
- 16 of 7222% booked
Project facts
| 2 BHK | 2 |
|---|---|
| 3 BHK | 1 |
| 4 BHK | 69 |
| Total units | 72 |
| Buildings | 3 |
| Land | 1 acre |
| Complaints on MahaRERA (filed by or against the builder) | 2 |
Since Dec 2025: final finishes 0% → 95% · complaints 1 → 2
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 95% | 16 | |
| 100% | 100% | 0% | — | |
| 0% | 0% | 0% | — |
"—" means MahaRERA shows no figure for that update.
About this project
The Luxe Towers - Building I and J (MahaRERA P52100015603) is a residential project by Neelsidhi Mohar Raisoni Developers LLP in Senapati Bapat Road, Pune 411016. It was launched in March 2018. It has 72 units in 3 buildings, with 2, 3 & 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2027, extended by 5 years from the original December 2022. Construction, averaged across its 3 buildings: excavation complete, structure (RCC) complete, final finishes 95% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.
16 of its 72 units are booked (22%).
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.