- Launched
- First of 2 phases
- Possession dates (MahaRERA)
- Jun 2026No phase has an extended possession date. What does Lapsed mean?
- Concrete structure (RCC)
- 100%Ready to move2 of 2 phases with structure completeWeighted across 2 phases
- Units booked
- 494 of 52394% booked
Facts
Project facts
| 1 BHK | 36 |
|---|---|
| 2 BHK | 387 |
| 3 BHK | 147 |
| Total units | 571 |
| Buildings | 8 |
| Land | 1.4 acres |
| Phases | 2 |
| MahaRERA complaints (filed by or against the builder) | 1 |
Since Dec 2025: booked 456 → 494
Shortlist 2 or more to compare side by side.
Phases
The 2 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| ARV Newtown Phase II Completed | P52100015904 | 198 | 100% | 99% | |
| ARV Newtown Phase III Ready to move Lapsed | P52100027214 | 372 | 100% | 80% |
Show updates by phase
ARV Newtown Phase II (P52100015904)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 80% | 80% | 76% | 198 | |
| 80% | 80% | 76% | 199 |
"—" means MahaRERA shows no figure for that update.
ARV Newtown Phase III (P52100027214)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 296 | |
| 100% | 100% | 90% | 258 | |
| 100% | 98% | 8% | 186 | |
| 100% | 85% | 0% | 186 | |
| 100% | 87% | 0% | 115 |
"—" means MahaRERA shows no figure for that update.
How to read construction stages
- Early stage
- The concrete structure (RCC) has not started yet.
- Mid-construction
- The concrete structure (RCC) is being built.
- Nearing possession
- The concrete structure (RCC) is complete and final finishes are below 90%.
- Ready to move
- MahaRERA shows the project Completed, or the concrete structure (RCC) is complete and final finishes are 90% or more.
- Concrete structure (RCC)
- The reinforced-concrete frame of the building: columns, beams and slabs.
- Final finishes
- Lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- Lapsed
- MahaRERA status when the possession date has passed with no extension or completion filed; it does not by itself mean work has stopped.
About this project
ARV Newtown is a project by Vedant Infracon in Pisoli, Pune 411028, registered with MahaRERA as 2 phases (P52100015904, P52100027214). The first phase was launched in April 2018. Together the phases have 571 units in 8 buildings, with 1, 2 & 3 BHK homes as registered with MahaRERA. On MahaRERA, 1 is completed and 1 is lapsed.
The registered possession date is June 2026; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 100% complete and final finishes 92% complete. 2 of the 2 phases have their structure complete.
494 of the 523 units reported for sale are booked (94%).