Renuka Gloria, Ravet

by Renuka Constructions. Ravet, Pune 412101. View on Google Maps

Launched
8 years 7 months promised
Possession date (MahaRERA)
2 months awayPossession date unchanged since launch
Concrete structure (RCC)
85%Mid-constructionAverage across 8 buildings
Units booked
394 of 63862% booked
Price per sq ft (incl. balconies and terrace)
₹8,0002026 so far · 16 salesup 4% on 202580% of the 2026 sales we found were at this rate or lessSee what buyers paid

Project facts

1 BHK206
2 BHK311
3 BHK84
Other units (shops, offices or not given by type)37
Total units638
Buildings8
Land4.4 acres
Landowner share41
Complaints on MahaRERA (filed by or against the builder)1

Since Dec 2025: booked 390 → 394 · structure 75% → 85% · final finishes 31% → 75% · complaints 0 → 1

Share on WhatsApp

What buyers paid here

From government sale records

The price per sq ft is the agreed price of the flat alone, counting balconies and terrace.

Flat sizes and prices

Flat sizeWhat most buyers paid
710 – 810 sq ft₹50 – 64 lakh

Based on flats sold in 2026 so far.

Price per sq ft, year by year

80% of the flats sold in each year went for this price or less.

2024₹7,400 per sq ft48 sales
2025up 4% on 2024₹7,700 per sq ft19 sales
2026 so farup 4% on 2025₹8,000 per sq ft16 sales

Rate vs other Ravet projects, 2026: about 10% lower

Studios (under 450 sq ft)

80% of the 2024 studio sales we found were at this rate or less

2024₹3,800 per sq ft12 sales

Sizes 420 – 430 sq ft. Studios are priced separately from flats and are not used in area price comparisons or Data Analytics.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
8 years 5 months of the promised 8 years 7 months have passed
Concrete structure (RCC) 85% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 75%Jun 2024: Excavation 75%Dec 2024: Excavation 75%Jun 2025: Excavation 75%Dec 2025: Excavation 75%Jul 2026: Excavation 88%Dec 2023: Concrete structure (RCC) 75%Jun 2024: Concrete structure (RCC) 75%Dec 2024: Concrete structure (RCC) 75%Jun 2025: Concrete structure (RCC) 75%Dec 2025: Concrete structure (RCC) 75%Jul 2026: Concrete structure (RCC) 85%Dec 2023: Final finishes 31%Jun 2024: Final finishes 31%Dec 2024: Final finishes 31%Jun 2025: Final finishes 31%Dec 2025: Final finishes 31%Jul 2026: Final finishes 75%Excavation 88%Concrete structure (RCC) 85%Final finishes 75%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
88%85%75%394
75%75%31%390
75%75%31%213

"—" means MahaRERA shows no figure for that update.

About this project

Renuka Gloria (MahaRERA P52100016508) is a residential project by Renuka Constructions in Ravet, Pune 412101. It was launched in May 2018. It has 638 units in 8 buildings: 601 homes (1, 2 & 3 BHK) and 37 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2026, unchanged since launch. Construction, averaged across its 8 buildings: excavation 88% complete, structure (RCC) 85% complete, final finishes 75% complete. MahaRERA records do not show it as ready to move in.

394 of its 638 units are booked (62%). Since the December 2025 update, 4 more units have been booked and the reported concrete structure (RCC) has gone from 75% to 85%. 80% of the 2026 (so far) sales we found here were at ₹8,000 per sq ft or less (up 4% on 2025), counting balconies and terrace in the size, based on 16 registered sales. Buyers here paid a rate about 10% lower than at other Ravet projects in 2026. Most buyers paid ₹50–64 lakh for flats of 710–810 sq ft. Its studios (under 450 sq ft) sold at ₹3,800 per sq ft or less in 2024 (12 sales); studios are priced separately from flats.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100016508.Check it on MahaRERA (P52100016508)All projects in Kiwale, Ravet