Skip to main content

Ravinanda Aamrai, Dhayari

by Om Sai Developers. Dhayari, Pune 411041. View on Google Maps

Launched
First of 2 phases
Possession dates (MahaRERA)
Dec 2024 – Dec 2028varies by phase2 of 2 phases have an extended possession date. Reading a project's possession date
Concrete structure (RCC)
100%Nearing possession2 of 2 phases with structure completeWeighted across 2 phases
Units booked
210 of 33962% booked

Project facts

1 BHK106
2 BHK233
Total units339
Buildings3
Land1.1 acres
Phases2
MahaRERA complaints (filed by or against the builder)21

Since Dec 2025: booked 175 → 210

Share on WhatsApp

Shortlist 2 or more to compare side by side.

The 2 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Ravinanda Aamrai Phase 1 Building C
Nearing possession
P52100016536126100%90%
Ravinanda Aamrai Phase II Building B2
Nearing possession
P52100028220213100%45%
Show updates by phase

Ravinanda Aamrai Phase 1 Building C (P52100016536)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%50%114
100%100%0%86
100%60%0%85

"—" means MahaRERA shows no figure for that update.

Ravinanda Aamrai Phase II Building B2 (P52100028220)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%25%96
100%88%50%89
100%60%0%81
100%60%0%61

"—" means MahaRERA shows no figure for that update.

How to read construction stages
Early stage
The concrete structure (RCC) has not started yet.
Mid-construction
The concrete structure (RCC) is being built.
Nearing possession
The concrete structure (RCC) is complete and final finishes are below 90%.
Ready to move
MahaRERA shows the project Completed, or the concrete structure (RCC) is complete and final finishes are 90% or more.
Concrete structure (RCC)
The reinforced-concrete frame of the building: columns, beams and slabs.
Final finishes
Lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
Lapsed
MahaRERA status when the possession date has passed with no extension or completion filed; it does not by itself mean work has stopped.

How to read construction stages

About this project

Ravinanda Aamrai is a project by Om Sai Developers in Dhayari, Pune 411041, registered with MahaRERA as 2 phases (P52100016536, P52100028220). The first phase was launched in May 2018. Together the phases have 339 units in 3 buildings, with 1 & 2 BHK homes as registered with MahaRERA. All 2 phases are active on MahaRERA.

The phases' registered possession dates run from December 2024 to December 2028; 2 of 2 phases have an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 100% complete and final finishes 34% complete. 2 of the 2 phases have their structure complete.

210 of the 339 units reported for sale are booked (62%).

Source: MahaRERA registrations P52100016536 and P52100028220.Open MahaRERA and search P52100016536All projects in Dhayari