Skyi Songbirds, Bhugaon

by Enerrgia Skyi Developers. Bhugaon, Pune 412115. View on Google Maps

Launched
First of 2 phases
Possession dates (MahaRERA)
Dec 2027 – Jun 2028varies by phase2 of 2 phases have an extended possession date. Reading a project's possession date
Concrete structure (RCC)
84%Mid-construction0 of 2 phases with structure completeWeighted across 2 phases
Units booked
105 of 25242% booked
Price per sq ft
₹9,0002026 salesdown 1% on 2025See what buyers paid

Project facts

2 BHK10
3 BHK242
Total units252
Buildings2
Land1.6 acres
Phases2
MahaRERA complaints (filed by or against the builder)5
Share on WhatsApp

Shortlist 2 or more to compare side by side.

What buyers paid here

From government sale records

What buyers paid in registered sales, not today's asking price. Use it to compare projects, then ask the builder for the current rate.

Flat types, sizes and prices

Flat typeSize (total internal area)What most buyers paidYear
2 BHKabout 860 – 890 sq ft₹77 – 78 lakh2026 sales
3 BHKabout 1,060 sq ft₹93 lakh – ₹1.01 crore2026 sales

Price per sq ft, year by year

2025₹9,100 per sq ft
2026down 1% on 2025₹9,000 per sq ft

Registered sales across all 2 phases.

Compared with the typical Bhugaon rate in 2026: about 5% lower

How to read this price
  • 80% of registered sales that year were at this rate or less.
  • Size is total internal area: carpet + balcony + terrace.
  • Higher floors, corner flats and open views usually cost more; lower floors and road-facing flats often less.
  • The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.
  • Fewer sales means a less certain figure.
  • Use it as a starting point for questions, not as an offer price.

Why this rate differs from other websites

The 2 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Skyi Songbirds Phase E
Mid-construction
P5210001934817291%48%
Skyi Songbirds Phase F
Mid-construction
P521000779568069%29%
Show updates by phase

Skyi Songbirds Phase E (P52100019348)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%91%0%82
100%68%0%82
100%2%0%54
100%0%0%37
100%0%0%30

"—" means MahaRERA shows no figure for that update.

Skyi Songbirds Phase F (P52100077956)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%69%0%23
100%0%0%23
0%0%0%—

"—" means MahaRERA shows no figure for that update.

How to read construction stages
Early stage
The concrete structure (RCC) has not started yet.
Mid-construction
The concrete structure (RCC) is being built.
Nearing possession
The concrete structure (RCC) is complete and final finishes are below 90%.
Ready to move
MahaRERA shows the project Completed, or the concrete structure (RCC) is complete and final finishes are 90% or more.
Concrete structure (RCC)
The reinforced-concrete frame of the building: columns, beams and slabs.
Final finishes
Lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
Lapsed
MahaRERA status when the possession date has passed with no extension or completion filed; it does not by itself mean work has stopped.

How to read construction stages

About this project

Skyi Songbirds is a project by Enerrgia Skyi Developers in Bhugaon, Pune 412115, registered with MahaRERA as 2 phases (P52100019348, P52100077956). The first phase was launched in January 2019. Together the phases have 252 units in 2 buildings, with 2 & 3 BHK homes as registered with MahaRERA. All 2 phases are active on MahaRERA.

The phases' registered possession dates run from December 2027 to June 2028; 2 of 2 phases have an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 84% complete and final finishes 0% complete. 0 of the 2 phases have their structure complete.

105 of the 252 units reported for sale are booked (42%). In 2026 registered sales, 80% of flats here sold at ₹9,000 per sq ft or less (down 1% on 2025), counting balconies and terrace in the size. Buyers here paid a rate about 5% lower than the typical Bhugaon rate in 2026. Most buyers paid ₹77–78 lakh for 2 BHK flats of about 860–890 sq ft (2026 sales); ₹93 lakh–₹1.01 crore for 3 BHK flats of about 1,060 sq ft (2026 sales). The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.

Skyi's track record in Pune

MahaRERA projects registered 2017–2026 in Pune & PCMC

Projects registered with MahaRERA41
Completed without extending the possession date17
Completed after an extension0
Lapsed7
Under construction17
Possession date extended on the builder's application7
Typical time from launch to 100% structure3 years 4 months
MahaRERA complaints (filed by or against the builder), all Skyi projects52 (20 of 41 projects)

See all Skyi projects →

Source: MahaRERA registrations P52100019348 and P52100077956.Open MahaRERA and search P52100019348All projects in Bhugaon, Bhukum, Pirangut, Lavale