- Launched
- 5 years 10 months originally promised
- Possession date (MahaRERA)
- 7 months ago. No further extension recordedExtended by 1 year (originally March 2025). What "Lapsed" means
- Concrete structure (RCC)
- 100%Nearing possession
- Units booked
- 71 of 13055% booked
Project facts
| 2 BHK | 65 |
|---|---|
| 3 BHK | 20 |
| Other units (shops, offices or not given by type) | 45 |
| Total units | 130 |
| Buildings | 1 |
| Land | 1.1 acres |
| Landowner share | 43 |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Since Dec 2025: booked 36 → 71 · structure 9% → 100% · final finishes 0% → 50% · total units 117 → 130
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 50% | 71 | |
| 100% | 9% | 0% | 36 |
"—" means MahaRERA shows no figure for that update.
About this project
Bhargav Stella (MahaRERA P52100020713) is a residential project by Bhargav Shelters in Dhankawadi, Pune 411043. It was launched in May 2019. It has 130 units in 1 building: 85 homes (2 & 3 BHK) and 45 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in March 2026, after an extension of 1 year from the original March 2025. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 50% complete. MahaRERA records do not show it as ready to move in.
71 of its 130 units are booked (55%). Since the December 2025 update, 35 more units have been booked and the reported concrete structure (RCC) has gone from 9% to 100%.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.