Sukhwani Skylines, Wakad

Finishing stage

Final finishes 100% · completion not yet filed on MahaRERA

by Sukhwani Chawla Developers. Wakad, Pune 411057. View on Google Maps

Launched
8 years 6 months promised
Possession date (MahaRERA)
1 year 2 months awayPossession date unchanged since launch
Concrete structure (RCC)
100%Finishing stageAverage across 9 buildings
Units booked
631 of 85374% booked
Price per sq ft (incl. balconies and terrace)
₹11,9002026 so far · 61 salesabout the same as 202580% of the 2026 sales we found were at this rate or lessSee what buyers paid

Project facts

1 BHK85
2 BHK549
3 BHK210
Other units (shops, offices or not given by type)9
Total units853
Buildings9
Land6.2 acres
Complaints on MahaRERA (filed by or against the builder)0
Share on WhatsApp

What buyers paid here

From government sale records

The price per sq ft is the agreed price of the flat alone, counting balconies and terrace.

Flat sizes and prices

Flat sizeWhat most buyers paid
760 sq ft₹82 – 90 lakh
900 – 940 sq ft₹97 lakh – ₹1.13 crore

Based on flats sold in 2026 so far.

Price per sq ft, year by year

80% of the flats sold in each year went for this price or less.

2024₹11,200 per sq ft95 sales
2025up 6% on 2024₹11,900 per sq ft77 sales
2026 so farabout the same as 2025₹11,900 per sq ft61 sales

Rate vs other Wakad projects, 2026: about 5% higher

Construction progress

As reported to MahaRERA at each update
Time used and structure built
7 years 4 months of the promised 8 years 6 months have passed
Concrete structure (RCC) 100% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 100%Jun 2024: Excavation 100%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 96%Jun 2024: Concrete structure (RCC) 63%Dec 2024: Concrete structure (RCC) 100%Jun 2025: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2023: Final finishes 62%Jun 2024: Final finishes 52%Dec 2024: Final finishes 100%Jun 2025: Final finishes 100%Dec 2025: Final finishes 100%Jul 2026: Final finishes 100%Excavation 100%Concrete structure (RCC) 100%Final finishes 100%

If a percentage drops between updates, we show it as MahaRERA reported it.

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%631
100%63%52%566
100%96%62%491

"—" means MahaRERA shows no figure for that update.

About this project

Sukhwani Skylines (MahaRERA P52100021183) is a residential project by Sukhwani Chawla Developers in Wakad, Pune 411057. It was launched in June 2019. It has 853 units in 9 buildings: 844 homes (1, 2 & 3 BHK) and 9 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2027, unchanged since launch. Construction, averaged across its 9 buildings: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete (structure and final finishes), but completion has not yet been recorded on MahaRERA.

631 of its 853 units are booked (74%). 80% of the 2026 (so far) sales we found here were at ₹11,900 per sq ft or less (about the same as 2025), counting balconies and terrace in the size, based on 61 registered sales. Buyers here paid a rate about 5% higher than at other Wakad projects in 2026. Most buyers paid ₹82–90 lakh for flats of 760 sq ft and ₹97 lakh–₹1.13 crore for 900–940 sq ft.

Sukhwani's track record in Pune

MahaRERA projects registered 2017–2026, in the 59 areas FlatNama covers

Projects registered with MahaRERA28
Completed without extending the possession date14
Completed after an extension, or lapsed3
Under construction11
Possession date extended by the builder4
Complaints on MahaRERA, all Sukhwani projects10 (4 of 28 projects)

See all Sukhwani projects →

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100021183.Check it on MahaRERA (P52100021183)All projects in Wakad, Hinjewadi, Marunji