41 Elite, Tathawade

Lapsed

by Krisala Enterprises. Tathawade, Pune 411033. View on Google Maps

Launched
First of 5 phases
Possession dates (MahaRERA)
Dec 20241 of 5 phases have an extended possession date. What does Lapsed mean?
Concrete structure (RCC)
100%Nearing possession5 of 5 phases with structure completeWeighted across 5 phases
Units booked
173 of 27762% booked
Price per sq ft
₹8,3002024 salesup 4% on 2023See what buyers paid

Project facts

1 BHK20
2 BHK182
3 BHK48
Total units277
Buildings5
Land1.5 acres
Phases5
MahaRERA complaints (filed by or against the builder)2
Share on WhatsApp

Shortlist 2 or more to compare side by side.

What buyers paid here

From government sale records

What buyers paid in registered sales, not today's asking price. Use it to compare projects, then ask the builder for the current rate.

Flat types, sizes and prices

Flat typeSize (total internal area)What most buyers paidYear
2 BHKabout 690 sq ft₹56 – 58 lakh2024 sales

Price per sq ft, year by year

2023₹8,000 per sq ft
2024up 4% on 2023₹8,300 per sq ft

Registered sales across all 5 phases.

Compared with the typical Tathawade rate in 2024: about 15% lower

How to read this price
  • 80% of registered sales that year were at this rate or less.
  • Size is total internal area: carpet + balcony + terrace.
  • Higher floors, corner flats and open views usually cost more; lower floors and road-facing flats often less.
  • The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.
  • Fewer sales means a less certain figure.
  • Use it as a starting point for questions, not as an offer price.

Why this rate differs from other websites

The 5 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
41 Elite A Building Phase 2
Completed
P5210002123464100%20%
41 Elite Phase 3 Building C
Ready to move Lapsed
P5210002749618100%24%
41 Elite
Completed
P5210002792960100%92%
41 Elite
Completed
P5210002795860100%88%
41 Elite
Completed
P5210002795948100%85%
Show updates by phase

41 Elite A Building Phase 2 (P52100021234)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%95%0%13

"—" means MahaRERA shows no figure for that update.

41 Elite Phase 3 Building C (P52100027496)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%95%11
100%100%80%11
100%80%0%11
100%80%0%5

"—" means MahaRERA shows no figure for that update.

41 Elite (P52100027929)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%60%0%55

"—" means MahaRERA shows no figure for that update.

41 Elite (P52100027958)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%60%0%53

"—" means MahaRERA shows no figure for that update.

41 Elite (P52100027959)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%60%0%41
100%60%0%32

"—" means MahaRERA shows no figure for that update.

How to read construction stages
Early stage
The concrete structure (RCC) has not started yet.
Mid-construction
The concrete structure (RCC) is being built.
Nearing possession
The concrete structure (RCC) is complete and final finishes are below 90%.
Ready to move
MahaRERA shows the project Completed, or the concrete structure (RCC) is complete and final finishes are 90% or more.
Concrete structure (RCC)
The reinforced-concrete frame of the building: columns, beams and slabs.
Final finishes
Lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
Lapsed
MahaRERA status when the possession date has passed with no extension or completion filed; it does not by itself mean work has stopped.

How to read construction stages

Other phases of this project

About this project

41 Elite is a project by Krisala Enterprises in Tathawade, Pune 411033, registered with MahaRERA as 5 phases (P52100021234, P52100027496, P52100027929, P52100027958, P52100027959). The first phase was launched in June 2019. Together the phases have 277 units in 5 buildings, with 1, 2 & 3 BHK homes as registered with MahaRERA. On MahaRERA, 4 are completed and 1 is lapsed.

The registered possession date is December 2024; 1 of 5 phases have an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 100% complete and final finishes 7% complete. 5 of the 5 phases have their structure complete.

173 of the 277 units reported for sale are booked (62%). In 2024 registered sales, 80% of flats here sold at ₹8,300 per sq ft or less (up 4% on 2023), counting balconies and terrace in the size. Buyers here paid a rate about 15% lower than the typical Tathawade rate in 2024. Most buyers paid ₹56–58 lakh for 2 BHK flats of about 690 sq ft (2024 sales). The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.

Source: MahaRERA registrations P52100021234, P52100027496, P52100027929, P52100027958 and P52100027959.Open MahaRERA and search P52100021234All projects in Tathawade, Punawale, Jambhe