Ravinanda 37, Kondhwa Khurd
by Ravinanda Icon Landmarks UNIT1. Kondhwa Khurd, Pune 411048. View on Google Maps
- Launched
- 5 years originally promised
- Possession date (MahaRERA)
- 5 months awayExtended by 2 years 9 months (originally June 2024). Why possession dates change
- Concrete structure (RCC)
- 100%Nearing possessionAverage across 2 buildings
- Units booked
- 70 of 10964% booked
Project facts
| 2 BHK | 46 |
|---|---|
| Other units (shops, offices or not given by type) | 63 |
| Total units | 109 |
| Name as registered on MahaRERA | RAVINANDA37 |
| Buildings | 2 |
| Land | 2 acres |
| Landowner share | 4 |
| Complaints on MahaRERA (filed by or against the builder) | 1 |
Since Dec 2025: structure 0% → 100% · final finishes 0% → 10% · possession date June 2024 → March 2027 · total units 98 → 109
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 10% | 70 | |
| 0% | 0% | 0% | — |
"—" means MahaRERA shows no figure for that update.
About this project
Ravinanda 37 (MahaRERA P52100021371) is a residential project by Ravinanda Icon Landmarks UNIT1 in Kondhwa Khurd, Pune 411048. It was launched in June 2019. It has 109 units in 2 buildings: 46 homes (2 BHK) and 63 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is March 2027, extended by 2 years 9 months from the original June 2024. Construction, averaged across its 2 buildings: excavation complete, structure (RCC) complete, final finishes 10% complete. MahaRERA records do not show it as ready to move in.
70 of its 109 units are booked (64%). Since the December 2025 update, the reported concrete structure (RCC) has gone from 0% to 100% and the possession date has moved from June 2024 to March 2027.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.