Skip to main content
← Back

Splendour County Wagholi

Lapsed

by PS Developers. Wagholi, Pune 412207. View on Google Maps

Launched
4 years 11 months originally promised
Possession date (MahaRERA)
1 year 4 months ago. No further extension recordedExtended by 1 year (originally June 2024). What "Lapsed" means
Concrete structure (RCC)
67%Mid-constructionAverage across 3 buildings
Units booked
130 of 14192% booked

Project facts

1 BHK13
2 BHK114
Other units (shops, offices or not given by type)14
Total units141
Buildings3
Land4 acres
Complaints on MahaRERA (filed by or against the builder)1

Since Dec 2025: booked 128 → 130 · structure 100% → 67% · final finishes 100% → 63%

Share on WhatsApp

Construction progress

As reported to MahaRERA at each update
Time used and structure built
All of the originally promised 4 years 11 months have passed
Concrete structure (RCC) 67% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 100%Jun 2024: Excavation 100%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 67%Dec 2023: Concrete structure (RCC) 95%Jun 2024: Concrete structure (RCC) 86%Dec 2024: Concrete structure (RCC) 100%Jun 2025: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 67%Dec 2023: Final finishes 68%Jun 2024: Final finishes 68%Dec 2024: Final finishes 88%Jun 2025: Final finishes 88%Dec 2025: Final finishes 100%Jul 2026: Final finishes 63%Excavation 67%Concrete structure (RCC) 67%Final finishes 63%

If a percentage drops between updates, we show it as MahaRERA reported it.

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
67%67%63%130
100%100%100%128
100%100%88%122
100%86%68%98
100%95%68%93

"—" means MahaRERA shows no figure for that update.

About this project

Splendour County Wagholi (MahaRERA P52100021548) is a residential project by PS Developers in Wagholi, Pune 412207. It was launched in July 2019. It has 141 units in 3 buildings: 127 homes (1 & 2 BHK) and 14 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in June 2025, after an extension of 1 year from the original June 2024. That date has passed and no further extension has been recorded. Construction, averaged across its 3 buildings: excavation 67% complete, structure (RCC) 67% complete, final finishes 63% complete. MahaRERA records do not show it as ready to move in.

130 of its 141 units are booked (92%). Since the December 2025 update, 2 more units have been booked and the reported concrete structure (RCC) has gone from 100% to 67%.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100021548.Check it on MahaRERA (P52100021548)All projects in Wagholi