The Collection - Residential W8, Vadgaon Sheri

Finishing stage

Final finishes 100% · completion not yet filed on MahaRERA

by Bramhacorp Limited. Vadgaon Sheri, Pune 411014. View on Google Maps

Launched
10 years 3 months promised
Possession date (MahaRERA)
3 years 2 months awayPossession date unchanged since launch
Concrete structure (RCC)
100%Finishing stage
Units booked
183 of 19494% booked
Price per sq ft (incl. balconies and terrace)
₹13,2002024 · 11 sales80% of the 2024 sales we found were at this rate or lessSee what buyers paid

Project facts

1 BHK4
2 BHK184
3 BHK2
Other units (shops, offices or not given by type)4
Total units194
Buildings1
Land0.2 acres
Complaints on MahaRERA (filed by or against the builder)0
Share on WhatsApp

What buyers paid here

From government sale records

The price per sq ft is the agreed price of the flat alone, counting balconies and terrace.

Flat sizes and prices

Flat sizeWhat most buyers paid
700 sq ft₹81 lakh – ₹1.02 crore

Based on flats sold in 2024.

Price per sq ft, year by year

80% of the flats sold in each year went for this price or less.

2024₹13,200 per sq ft11 sales

Construction progress

As reported to MahaRERA at each update
Time used and structure built
7 years 1 month of the promised 10 years 3 months have passed
Concrete structure (RCC) 100% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 100%Jun 2024: Excavation 100%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 100%Jun 2024: Concrete structure (RCC) 100%Dec 2024: Concrete structure (RCC) 100%Jun 2025: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2023: Final finishes 55%Jun 2024: Final finishes 92%Dec 2024: Final finishes 100%Jun 2025: Final finishes 100%Dec 2025: Final finishes 100%Jul 2026: Final finishes 100%Excavation 100%Concrete structure (RCC) 100%Final finishes 100%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%183
100%100%92%182
100%100%55%167

"—" means MahaRERA shows no figure for that update.

About this project

The Collection - Residential W8 (MahaRERA P52100022277) is a residential project by Bramhacorp Limited in Vadgaon Sheri, Pune 411014. It was launched in September 2019. It has 194 units in 1 building: 190 homes (1, 2 & 3 BHK) and 4 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2029, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete (structure and final finishes), but completion has not yet been recorded on MahaRERA.

183 of its 194 units are booked (94%). 80% of the 2024 sales we found here were at ₹13,200 per sq ft or less, counting balconies and terrace in the size, based on 11 registered sales. Most buyers paid ₹81 lakh–₹1.02 crore for flats of 700 sq ft.

Bramhacorp's track record in Pune

MahaRERA projects registered 2017–2026, in the 59 areas FlatNama covers

Projects registered with MahaRERA15
Completed without extending the possession date4
Completed after an extension, or lapsed0
Under construction11
Possession date extended by the builder0
Typical time from launch to 100% structure3 years 2 months
Complaints on MahaRERA, all Bramhacorp projects3 (3 of 15 projects)

See all Bramhacorp projects →

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100022277.Check it on MahaRERA (P52100022277)All projects in Kharadi, Vadgaon Sheri, Viman Nagar