VTP Beaumonde, Manjari Khurd

Lapsed

by Arhum Erectors Private Limited. Manjari Khurd, Pune 412307. View on Google Maps

Launched
First of 2 phases
Possession dates (MahaRERA)
Jun 2025No phase has an extended possession date. What does Lapsed mean?
Concrete structure (RCC)
100%Nearing possession2 of 2 phases with structure completeWeighted across 2 phases
Units booked
473 of 47899% booked
Price per sq ft
₹10,9002025 salesSee what buyers paid

Project facts

2 BHK316
3 BHK162
Total units478
Buildings2
Land0.4 acres
Phases2
MahaRERA complaints (filed by or against the builder)8
Share on WhatsApp

Shortlist 2 or more to compare side by side.

What buyers paid here

From government sale records

What buyers paid in registered sales, not today's asking price. Use it to compare projects, then ask the builder for the current rate.

Flat types, sizes and prices

Flat typeSize (total internal area)What most buyers paidYear
2 BHKabout 710 – 780 sq ft₹75 – 82 lakh2025 sales
3 BHKabout 970 – 1,090 sq ft₹1.13 – 1.21 crore2025 sales

Price per sq ft, year by year

2023₹8,900 per sq ft
2025₹10,900 per sq ft

Registered sales across all 2 phases.

Compared with the typical Manjari Khurd rate in 2025: about 5% lower

How to read this price
  • 80% of registered sales that year were at this rate or less.
  • Size is total internal area: carpet + balcony + terrace.
  • Higher floors, corner flats and open views usually cost more; lower floors and road-facing flats often less.
  • The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.
  • Fewer sales means a less certain figure.
  • Use it as a starting point for questions, not as an offer price.

Why this rate differs from other websites

The 2 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
VTP Beaumonde Building T3
Completed
P52100022781212100%99%
VTP Beaumonde Building T2
Nearing possession Lapsed
P52100025232266100%99%
Show updates by phase

VTP Beaumonde Building T3 (P52100022781)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%90%210
100%100%70%210
100%97%13%182

"—" means MahaRERA shows no figure for that update.

VTP Beaumonde Building T2 (P52100025232)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%78%263
100%100%75%263
100%96%13%225

"—" means MahaRERA shows no figure for that update.

How to read construction stages
Early stage
The concrete structure (RCC) has not started yet.
Mid-construction
The concrete structure (RCC) is being built.
Nearing possession
The concrete structure (RCC) is complete and final finishes are below 90%.
Ready to move
MahaRERA shows the project Completed, or the concrete structure (RCC) is complete and final finishes are 90% or more.
Concrete structure (RCC)
The reinforced-concrete frame of the building: columns, beams and slabs.
Final finishes
Lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
Lapsed
MahaRERA status when the possession date has passed with no extension or completion filed; it does not by itself mean work has stopped.

How to read construction stages

About this project

VTP Beaumonde is a project by Arhum Erectors Private Limited in Manjari Khurd, Pune 412307, registered with MahaRERA as 2 phases (P52100022781, P52100025232). The first phase was launched in October 2019. Together the phases have 478 units in 2 buildings, with 2 & 3 BHK homes as registered with MahaRERA. On MahaRERA, 1 is completed and 1 is lapsed.

The registered possession date is June 2025; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 100% complete and final finishes 83% complete. 2 of the 2 phases have their structure complete.

473 of the 478 units reported for sale are booked (99%). In 2025 registered sales, 80% of flats here sold at ₹10,900 per sq ft or less, counting balconies and terrace in the size. Buyers here paid a rate about 5% lower than the typical Manjari Khurd rate in 2025. Most buyers paid ₹75–82 lakh for 2 BHK flats of about 710–780 sq ft (2025 sales); ₹1.13–1.21 crore for 3 BHK flats of about 970–1,090 sq ft (2025 sales). The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.

Source: MahaRERA registrations P52100022781 and P52100025232.Open MahaRERA and search P52100022781All projects in Manjari, Shewalewadi