Namoville, Balewadi
by Royal Namoville Ventures. Balewadi, Pune 411045. View on Google Maps
- Launched
- 4 years 6 months originally promised
- Possession date (MahaRERA)
- 1 year 6 months ago. No further extension recordedExtended by 1 year (originally April 2024). Why possession dates change
- Concrete structure (RCC)
- 100%Nearing possessionAverage across 2 buildings
- Units booked
- 112 of 11895% booked
Project facts
| 1 BHK | 4 |
|---|---|
| 2 BHK | 86 |
| 3 BHK | 28 |
| Total units | 118 |
| Buildings | 2 |
| Land | 1.3 acres |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Since Dec 2025: booked 77 → 112 · final finishes 50% → 53% · total units 120 → 118
Compared with 3 similar projects in PIN 411045
Projects with 50–250 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 4 yrs 6 mths | 6 yrs 2 mths |
| Possession date extended | By 1 year | 0 of 3 |
| Possession date passed | Yes, due April 2025 | 3 ready to move; 0 also past their date |
| Concrete structure (RCC) complete | 100% | 100% |
| Share of units booked | 95% | 95% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Majestique Signature Towers C2 | December 2019 | June 2025 | 100% | 49 of 62 booked (79%) |
| Aldea Espanola Phase VIII | January 2020 | March 2026 | 100% | 87 of 88 booked (99%) |
| Espacio - A and B | March 2020 | December 2026 | 100% | 91 of 96 booked (95%) |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 53% | 112 | |
| 100% | 100% | 50% | 77 | |
| 100% | 88% | 50% | 62 |
"—" means MahaRERA shows no figure for that update.
About this project
Namoville (MahaRERA P52100022808) is a residential project by Royal Namoville Ventures in Balewadi, Pune 411045. It was launched in October 2019. It has 118 units in 2 buildings, with 1, 2 & 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Possession was due in April 2025, after an extension of 1 year from the original April 2024. That date has passed and no further extension has been recorded. Construction, averaged across its 2 buildings: excavation complete, structure (RCC) complete, final finishes 53% complete. MahaRERA records do not show it as ready to move in.
112 of its 118 units are booked (95%). Since the December 2025 update, 35 more units have been booked.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.