Advika, Pisoli
by Advika Constructions Pvt.ltd. Pisoli, Pune 411048. View on Google Maps
- Launched
- First of 3 phases
- Possession dates (MahaRERA)
- Mar 2028 – Dec 2030varies by phase1 of 3 phases have an extended possession date. Reading a project's possession date
- Concrete structure (RCC)
- 74%Mid-construction2 of 3 phases with structure completeWeighted across 3 phases
- Units booked
- 138 of 17878% booked · 1 phase not reported
Facts
Project facts
| 1 BHK | 86 |
|---|---|
| 2 BHK | 148 |
| Total units | 238 |
| Buildings | 3 |
| Land | 6.9 acres |
| Phases | 3 |
| MahaRERA complaints (filed by or against the builder) | 0 |
Since Dec 2025: booked 132 → 138
Shortlist 2 or more to compare side by side.
Phases
The 3 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| Advika Phase III - E Completed | P52100022868 | 87 | 100% | 89% | |
| Advika Phase III - F Ready to move | P52100051370 | 87 | 100% | 66% | |
| Advika Phase IV-C Early stage | PR1260002600100 | 60 | 0% | Not reported |
Show updates by phase
Advika Phase III - E (P52100022868)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 95% | 81 | |
| 100% | 100% | 95% | 79 | |
| 100% | 100% | 0% | 76 |
"—" means MahaRERA shows no figure for that update.
Advika Phase III - F (P52100051370)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 57 | |
| 100% | 100% | 100% | 51 | |
| 100% | 100% | 0% | 31 | |
| 100% | 100% | 0% | 21 | |
| 100% | 75% | 0% | — |
"—" means MahaRERA shows no figure for that update.
Advika Phase IV-C (PR1260002600100)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 0% | 0% | — |
"—" means MahaRERA shows no figure for that update.
How to read construction stages
- Early stage
- The concrete structure (RCC) has not started yet.
- Mid-construction
- The concrete structure (RCC) is being built.
- Nearing possession
- The concrete structure (RCC) is complete and final finishes are below 90%.
- Ready to move
- MahaRERA shows the project Completed, or the concrete structure (RCC) is complete and final finishes are 90% or more.
- Concrete structure (RCC)
- The reinforced-concrete frame of the building: columns, beams and slabs.
- Final finishes
- Lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- Lapsed
- MahaRERA status when the possession date has passed with no extension or completion filed; it does not by itself mean work has stopped.
About this project
Advika is a project by Advika Constructions Pvt.ltd in Pisoli, Pune 411048, registered with MahaRERA as 3 phases (P52100022868, P52100051370, PR1260002600100). The first phase was launched in November 2019. Together the phases have 238 units in 3 buildings, with 1 & 2 BHK homes as registered with MahaRERA. On MahaRERA, 2 are active and 1 is completed.
The phases' registered possession dates run from March 2028 to December 2030; 1 of 3 phases have an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 74% complete and final finishes 73% complete. 2 of the 3 phases have their structure complete.
138 of the 178 units reported for sale are booked (78%); 1 phase has not reported bookings.