47 East, Mundhwa

by Kumar Properties and Developers LLP. Mundhwa, Pune 411036. View on Google Maps

Launched
First of 3 phases
Possession dates (MahaRERA)
Mar 2027 – Dec 2028varies by phaseNo phase has an extended possession date
Concrete structure (RCC)
85%Mid-construction2 of 3 phases with structure completeWeighted across 3 phases
Units booked
263 of 29988% booked
Price per sq ft
₹11,0002026 salesup 3% on 2025See what buyers paid

Project facts

2 BHK173
3 BHK126
Total units299
Buildings5
Land5.7 acres
Phases3
MahaRERA complaints (filed by or against the builder)55

Since Dec 2025: booked 265 → 263

Share on WhatsApp

Shortlist 2 or more to compare side by side.

What buyers paid here

From government sale records

What buyers paid in registered sales, not today's asking price. Use it to compare projects, then ask the builder for the current rate.

Flat types, sizes and prices

Flat typeSize (total internal area)What most buyers paidYear
2 BHKabout 780 sq ft₹70 – 72 lakh2023 sales
3 BHKabout 1,010 – 1,230 sq ft₹1.19 – 1.37 crore2026 sales

Price per sq ft, year by year

2023₹9,600 per sq ft
2024up 14% on 2023₹10,900 per sq ft
2025down 2% on 2024₹10,700 per sq ft
2026up 3% on 2025₹11,000 per sq ft

Registered sales across all 3 phases.

Compared with the typical Mundhwa rate in 2026: about 15% lower

How to read this price
  • 80% of registered sales that year were at this rate or less.
  • Size is total internal area: carpet + balcony + terrace.
  • Higher floors, corner flats and open views usually cost more; lower floors and road-facing flats often less.
  • The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.
  • Fewer sales means a less certain figure.
  • Use it as a starting point for questions, not as an offer price.

Why this rate differs from other websites

The 3 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
47 East - A
Nearing possession
P52100024598173100%100%
47 East - B Wing A
Nearing possession
P5210004770263100%87%
47 East - B Wing B, C and D
Mid-construction
P521000529556329%56%
Show updates by phase

47 East - A (P52100024598)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%50%173
100%100%34%173
100%100%27%173
100%100%4%173
100%100%0%173

"—" means MahaRERA shows no figure for that update.

47 East - B Wing A (P52100047702)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%0%55
100%83%0%55
100%58%0%55
100%29%0%55

"—" means MahaRERA shows no figure for that update.

47 East - B Wing B, C and D (P52100052955)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%29%0%35
100%27%0%37
100%15%0%23
100%11%0%12
100%3%0%9

"—" means MahaRERA shows no figure for that update.

How to read construction stages
Early stage
The concrete structure (RCC) has not started yet.
Mid-construction
The concrete structure (RCC) is being built.
Nearing possession
The concrete structure (RCC) is complete and final finishes are below 90%.
Ready to move
MahaRERA shows the project Completed, or the concrete structure (RCC) is complete and final finishes are 90% or more.
Concrete structure (RCC)
The reinforced-concrete frame of the building: columns, beams and slabs.
Final finishes
Lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
Lapsed
MahaRERA status when the possession date has passed with no extension or completion filed; it does not by itself mean work has stopped.

How to read construction stages

Other phases of this project

About this project

47 East is a project by Kumar Properties and Developers LLP in Mundhwa, Pune 411036, registered with MahaRERA as 3 phases (P52100024598, P52100047702, P52100052955). The first phase was launched in February 2020. Together the phases have 299 units in 5 buildings, with 2 & 3 BHK homes as registered with MahaRERA. All 3 phases are active on MahaRERA.

The phases' registered possession dates run from March 2027 to December 2028; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 85% complete and final finishes 29% complete. 2 of the 3 phases have their structure complete.

263 of the 299 units reported for sale are booked (88%). In 2026 registered sales, 80% of flats here sold at ₹11,000 per sq ft or less (up 3% on 2025), counting balconies and terrace in the size. Buyers here paid a rate about 15% lower than the typical Mundhwa rate in 2026. Most buyers paid ₹70–72 lakh for 2 BHK flats of about 780 sq ft (2023 sales); ₹1.19–1.37 crore for 3 BHK flats of about 1,010–1,230 sq ft (2026 sales). The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.

Kumar's track record in Pune

MahaRERA projects registered 2017–2026 in Pune & PCMC

Projects registered with MahaRERA82
Completed without extending the possession date42
Completed after an extension2
Lapsed3
Under construction35
Possession date extended on the builder's application5
Typical time from launch to 100% structure2 years 6 months
MahaRERA complaints (filed by or against the builder), all Kumar projects71 (8 of 82 projects)

See all Kumar projects →

Source: MahaRERA registrations P52100024598, P52100047702 and P52100052955.Open MahaRERA and search P52100024598All projects in Mundhwa, Keshavnagar