Skip to main content

Palm Spring, Ravet

by Aryavedant promoters & builders. Ravet, Pune 412101. View on Google Maps

Launched
First of 2 phases
Possession dates (MahaRERA)
Jun 2024 – May 2028varies by phase1 of 2 phases have an extended possession date. Reading a project's possession date
Concrete structure (RCC)
90%Mid-construction1 of 2 phases with structure completeWeighted across 2 phases
Units booked
115 of 20456% booked
Price per sq ft
₹8,2002026 salesdown 1% on 2025See what buyers paid

Project facts

1 RK6
1 BHK65
2 BHK128
Total units204
Buildings4
Land1.7 acres
Phases2
MahaRERA complaints (filed by or against the builder)0
Share on WhatsApp

Shortlist 2 or more to compare side by side.

What buyers paid here

From government sale records

What buyers paid in registered sales, not today's asking price. Use it to compare projects, then ask the builder for the current rate.

Flat types, sizes and prices

Flat typeSize (total internal area)What most buyers paidYear
1 RK / 1 BHKabout 490 – 520 sq ft₹34 – 35 lakh2023 sales
2 BHKabout 820 sq ft₹59 – 68 lakh2026 sales

Price per sq ft, year by year

2023₹6,900 per sq ft
2024up 12% on 2023₹7,700 per sq ft
2025up 8% on 2024₹8,300 per sq ft
2026down 1% on 2025₹8,200 per sq ft

Registered sales across all 2 phases.

Compared with the typical Ravet rate in 2026: about 15% lower

How to read this price
  • 80% of registered sales that year were at this rate or less.
  • Size is total internal area: carpet + balcony + terrace.
  • Higher floors, corner flats and open views usually cost more; lower floors and road-facing flats often less.
  • The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.
  • Fewer sales means a less certain figure.
  • Use it as a starting point for questions, not as an offer price.

Why this rate differs from other websites

The 2 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Palm Spring A, B, E
Nearing possession Lapsed
P52100026083155100%60%
Palm Spring D Wing
Mid-construction
P521000513793850%39%
Show updates by phase

Palm Spring A, B, E (P52100026083)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%88%100
100%87%0%92

"—" means MahaRERA shows no figure for that update.

Palm Spring D Wing (P52100051379)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%50%0%15
100%50%0%—
100%0%0%—

"—" means MahaRERA shows no figure for that update.

How to read construction stages
Early stage
The concrete structure (RCC) has not started yet.
Mid-construction
The concrete structure (RCC) is being built.
Nearing possession
The concrete structure (RCC) is complete and final finishes are below 90%.
Ready to move
MahaRERA shows the project Completed, or the concrete structure (RCC) is complete and final finishes are 90% or more.
Concrete structure (RCC)
The reinforced-concrete frame of the building: columns, beams and slabs.
Final finishes
Lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
Lapsed
MahaRERA status when the possession date has passed with no extension or completion filed; it does not by itself mean work has stopped.

How to read construction stages

About this project

Palm Spring is a project by Aryavedant promoters & builders in Ravet, Pune 412101, registered with MahaRERA as 2 phases (P52100026083, P52100051379). The first phase was launched in August 2020. Together the phases have 204 units in 4 buildings, with 1 RK, 1 BHK & 2 BHK homes as registered with MahaRERA. On MahaRERA, 1 is lapsed and 1 is active.

The phases' registered possession dates run from June 2024 to May 2028; 1 of 2 phases have an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 90% complete and final finishes 71% complete. 1 of the 2 phases have their structure complete.

115 of the 204 units reported for sale are booked (56%). In 2026 registered sales, 80% of flats here sold at ₹8,200 per sq ft or less (down 1% on 2025), counting balconies and terrace in the size. Buyers here paid a rate about 15% lower than the typical Ravet rate in 2026. Most buyers paid ₹34–35 lakh for 1 RK / 1 BHK flats of about 490–520 sq ft (2023 sales); ₹59–68 lakh for 2 BHK flats of about 820 sq ft (2026 sales). The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.

Source: MahaRERA registrations P52100026083 and P52100051379.Open MahaRERA and search P52100026083All projects in Kiwale, Ravet