Skip to main content
← Back

Star Vista, Ravet

Lapsed

by Ravie Khilumal Ochanni. Ravet, Pune 412101. View on Google Maps

Launched
3 years 1 month promised
Possession date (MahaRERA)
3 years 1 month ago. No extension recordedPossession date unchanged since launch. What "Lapsed" means
Concrete structure (RCC)
100%Nearing possessionAverage across 3 buildings
Units booked
169 of 19885% booked

Project facts

1 BHK6
2 BHK190
Other units (shops, offices or not given by type)2
Total units198
Buildings3
Land2.6 acres
Complaints on MahaRERA (filed by or against the builder)1
Share on WhatsApp

Construction progress

As reported to MahaRERA at each update
Time used and structure built
All of the promised 3 years 1 month have passed
Concrete structure (RCC) 100% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 100%Jun 2024: Excavation 100%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 100%Jun 2024: Concrete structure (RCC) 100%Dec 2024: Concrete structure (RCC) 100%Jun 2025: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2023: Final finishes 67%Jun 2024: Final finishes 67%Dec 2024: Final finishes 67%Jun 2025: Final finishes 67%Dec 2025: Final finishes 67%Jul 2026: Final finishes 67%Excavation 100%Concrete structure (RCC) 100%Final finishes 67%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%67%169
100%100%67%168

"—" means MahaRERA shows no figure for that update.

Other phases of this project

About this project

Star Vista (MahaRERA P52100026112) is a residential project by Ravie Khilumal Ochanni in Ravet, Pune 412101. It was launched in August 2020. It has 198 units in 3 buildings: 196 homes (1 & 2 BHK) and 2 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in September 2023. That date has passed and no extension has been recorded. Construction, averaged across its 3 buildings: excavation complete, structure (RCC) complete, final finishes 67% complete. MahaRERA records do not show it as ready to move in.

169 of its 198 units are booked (85%).

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100026112.Check it on MahaRERA (P52100026112)All projects in Kiwale, Ravet