Urban Skyline, Ravet

by Urban Space Creators. Ravet, Pune 412101. View on Google Maps

Launched
First of 2 phases
Possession dates (MahaRERA)
Jun 2027 – Dec 2027varies by phase1 of 2 phases have an extended possession date. Reading a project's possession date
Concrete structure (RCC)
88%Mid-construction0 of 2 phases with structure completeWeighted across 2 phases
Units booked
443 of 1,00344% booked
Price per sq ft
₹9,4002026 salesup 3% on 2025See what buyers paid

Project facts

2 BHK675
3 BHK278
Total units1,003
Buildings7
Land3.4 acres
Phases2
MahaRERA complaints (filed by or against the builder)33
Share on WhatsApp

Shortlist 2 or more to compare side by side.

What buyers paid here

From government sale records

What buyers paid in registered sales, not today's asking price. Use it to compare projects, then ask the builder for the current rate.

Flat types, sizes and prices

Flat typeSize (total internal area)What most buyers paidYear
1 RK / 1 BHKabout 590 sq ft₹28 lakh2024 sales
2 BHKabout 770 – 800 sq ft₹64 – 76 lakh2026 sales
3 BHKabout 1,040 – 1,100 sq ft₹86 lakh – ₹1.04 crore2026 sales

Price per sq ft, year by year

2023₹8,200 per sq ft
2024up 6% on 2023₹8,700 per sq ft
2025up 5% on 2024₹9,100 per sq ft
2026up 3% on 2025₹9,400 per sq ft

Registered sales across all 2 phases.

Compared with the typical Ravet rate in 2026: similar

How to read this price
  • 80% of registered sales that year were at this rate or less.
  • Size is total internal area: carpet + balcony + terrace.
  • Higher floors, corner flats and open views usually cost more; lower floors and road-facing flats often less.
  • The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.
  • Fewer sales means a less certain figure.
  • Use it as a starting point for questions, not as an offer price.

Why this rate differs from other websites

The 2 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Urban Skyline Phase I
Mid-construction
P5210002649940898%36%
Urban Skyline Phase II
Mid-construction
P5210003104354580%50%
Show updates by phase

Urban Skyline Phase I (P52100026499)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%98%38%147

"—" means MahaRERA shows no figure for that update.

Urban Skyline Phase II (P52100031043)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%80%0%296
100%37%0%296
100%0%0%296

"—" means MahaRERA shows no figure for that update.

How to read construction stages
Early stage
The concrete structure (RCC) has not started yet.
Mid-construction
The concrete structure (RCC) is being built.
Nearing possession
The concrete structure (RCC) is complete and final finishes are below 90%.
Ready to move
MahaRERA shows the project Completed, or the concrete structure (RCC) is complete and final finishes are 90% or more.
Concrete structure (RCC)
The reinforced-concrete frame of the building: columns, beams and slabs.
Final finishes
Lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
Lapsed
MahaRERA status when the possession date has passed with no extension or completion filed; it does not by itself mean work has stopped.

How to read construction stages

About this project

Urban Skyline is a project by Urban Space Creators in Ravet, Pune 412101, registered with MahaRERA as 2 phases (P52100026499, P52100031043). The first phase was launched in September 2020. Together the phases have 1,003 units in 7 buildings, with 2 & 3 BHK homes as registered with MahaRERA. All 2 phases are active on MahaRERA.

The phases' registered possession dates run from June 2027 to December 2027; 1 of 2 phases have an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 88% complete and final finishes 16% complete. 0 of the 2 phases have their structure complete.

443 of the 1,003 units reported for sale are booked (44%). In 2026 registered sales, 80% of flats here sold at ₹9,400 per sq ft or less (up 3% on 2025), counting balconies and terrace in the size. Buyers here paid a rate similar to the typical Ravet rate in 2026. Most buyers paid ₹28 lakh for 1 RK / 1 BHK flats of about 590 sq ft (2024 sales); ₹64–76 lakh for 2 BHK flats of about 770–800 sq ft (2026 sales); ₹86 lakh–₹1.04 crore for 3 BHK flats of about 1,040–1,100 sq ft (2026 sales). The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.

Source: MahaRERA registrations P52100026499 and P52100031043.Open MahaRERA and search P52100026499All projects in Kiwale, Ravet