Joyville Hadapsar Annexe, Shewalewadi

by Joyville Shapoorji Housing Private Limited. Shewalewadi, Pune 412307. View on Google Maps

Launched
First of 14 phases
Possession dates (MahaRERA)
Jun 2025 – Dec 2027varies by phase1 of 14 phases have an extended possession date. Reading a project's possession date
Concrete structure (RCC)
98%Mid-construction11 of 14 phases with structure completeWeighted across 14 phases
Units booked
1,790 of 2,01089% booked

Project facts

1 BHK444
2 BHK1,125
3 BHK381
Total units2,010
Buildings16
Land0.5 acres
Phases14
MahaRERA complaints (filed by or against the builder)1

Since Dec 2025: booked 1,774 → 1,790

Share on WhatsApp

Shortlist 2 or more to compare side by side.

The 14 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Joyville Hadapsar Annexe Phase 6
Completed
P52100026779132100%92%
Joyville Hadapsar Annexe Phase 8
Mid-construction Lapsed
P5210002678513297%94%
Joyville Hadapsar Annexe Phase 10
Completed
P52100026795132100%100%
Joyville Hadapsar Annexe Phase 9
Completed
P52100026797132100%99%
Joyville Hadapsar Annexe Phase 7
Mid-construction Lapsed
P5210002680013298%100%
Joyville Hadapsar Annexe Phase 12
Ready to move Lapsed
P52100028308132100%100%
Joyville Hadapsar Annexe Phase 11
Nearing possession Lapsed
P52100028311132100%91%
Joyville Hadapsar Annexe Phase 13
Nearing possession Lapsed
P52100031391132100%98%
Joyville Hadapsar Annexe Phase 14
Completed
P52100031515132100%100%
Joyville Hadapsar Annexe Phase 15
Nearing possession Lapsed
P52100034911132100%100%
Joyville Hadapsar Annexe Phase 18
Nearing possession
P521000483140100%83%
Joyville Hadapsar Annexe Phase 20
Nearing possession
P52100048377126100%82%
Joyville Hadapsar Annexe Phase 16
Nearing possession
P52100049970252100%99%
Joyville Hadapsar Annexe Phase 17
Mid-construction
P5210005417425285%40%
Show updates by phase

Joyville Hadapsar Annexe Phase 6 (P52100026779)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%40%122
100%100%40%121

"—" means MahaRERA shows no figure for that update.

Joyville Hadapsar Annexe Phase 8 (P52100026785)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%97%89%124
100%100%75%122
100%100%8%117

"—" means MahaRERA shows no figure for that update.

Joyville Hadapsar Annexe Phase 10 (P52100026795)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%88%132
100%100%81%126
100%100%33%126

"—" means MahaRERA shows no figure for that update.

Joyville Hadapsar Annexe Phase 9 (P52100026797)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%98%92%131
100%100%74%127
100%100%33%123

"—" means MahaRERA shows no figure for that update.

Joyville Hadapsar Annexe Phase 7 (P52100026800)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%98%90%132
100%100%73%128
100%100%36%128

"—" means MahaRERA shows no figure for that update.

Joyville Hadapsar Annexe Phase 12 (P52100028308)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%90%132
100%100%43%123
100%100%13%105
100%22%0%102

"—" means MahaRERA shows no figure for that update.

Joyville Hadapsar Annexe Phase 11 (P52100028311)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%43%120
100%100%43%124
100%100%13%114
100%57%0%109

"—" means MahaRERA shows no figure for that update.

Joyville Hadapsar Annexe Phase 13 (P52100031391)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%43%129
100%100%43%122
100%100%43%114
100%100%0%104

"—" means MahaRERA shows no figure for that update.

Joyville Hadapsar Annexe Phase 14 (P52100031515)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%13%132
100%100%13%128
100%100%13%124
100%65%0%113

"—" means MahaRERA shows no figure for that update.

Joyville Hadapsar Annexe Phase 15 (P52100034911)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%85%132
100%100%75%132
100%100%13%128
100%100%13%115
100%30%0%105

"—" means MahaRERA shows no figure for that update.

Joyville Hadapsar Annexe Phase 18 (P52100048314)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%35%50
100%100%25%46
100%54%0%40
100%25%0%30
100%0%0%16

"—" means MahaRERA shows no figure for that update.

Joyville Hadapsar Annexe Phase 20 (P52100048377)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%35%103
100%85%25%92
100%24%0%74
100%11%0%59
100%0%0%31

"—" means MahaRERA shows no figure for that update.

Joyville Hadapsar Annexe Phase 16 (P52100049970)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%78%250
100%100%50%249
100%54%0%223
100%28%0%215
100%0%0%134

"—" means MahaRERA shows no figure for that update.

Joyville Hadapsar Annexe Phase 17 (P52100054174)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%85%25%101
100%16%0%47
100%5%0%—
0%0%0%—

"—" means MahaRERA shows no figure for that update.

How to read construction stages
Early stage
The concrete structure (RCC) has not started yet.
Mid-construction
The concrete structure (RCC) is being built.
Nearing possession
The concrete structure (RCC) is complete and final finishes are below 90%.
Ready to move
MahaRERA shows the project Completed, or the concrete structure (RCC) is complete and final finishes are 90% or more.
Concrete structure (RCC)
The reinforced-concrete frame of the building: columns, beams and slabs.
Final finishes
Lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
Lapsed
MahaRERA status when the possession date has passed with no extension or completion filed; it does not by itself mean work has stopped.

How to read construction stages

About this project

Joyville Hadapsar Annexe is a project by Joyville Shapoorji Housing Private Limited in Shewalewadi, Pune 412307, registered with MahaRERA as 14 phases (P52100026779, P52100026785, P52100026795, P52100026797, P52100026800, P52100028308, P52100028311, P52100031391, P52100031515, P52100034911, P52100048314, P52100048377, P52100049970, P52100054174). The first phase was launched in October 2020. Together the phases have 2,010 units in 16 buildings, with 1, 2 & 3 BHK homes as registered with MahaRERA. On MahaRERA, 6 are lapsed, 4 are completed and 4 are active.

The phases' registered possession dates run from June 2025 to December 2027; 1 of 14 phases have an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 98% complete and final finishes 60% complete. 11 of the 14 phases have their structure complete.

1,790 of the 2,010 units reported for sale are booked (89%).

Source: MahaRERA registrations P52100026779, P52100026785, P52100026795, P52100026797, P52100026800, P52100028308, P52100028311, P52100031391, P52100031515, P52100034911, P52100048314, P52100048377, P52100049970 and P52100054174.Open MahaRERA and search P52100026779All projects in Manjari, Shewalewadi