Destination Ostia Bldg H1 and Commercial Bldg 2, Charholi
Lapsed
by D R Gavhane Landmarks LLP. Charholi, Pune 412105. View on Google Maps
- Launched
- 4 years promised
- Possession date (MahaRERA)
- 1 year 10 months ago. No extension recordedPossession date unchanged since launch. What "Lapsed" means
- Concrete structure (RCC)
- 100%Nearing possession
- Units booked
- 86 of 10979% booked
Project facts
| 2 BHK | 72 |
|---|---|
| 3 BHK | 24 |
| Other units (shops, offices or not given by type) | 13 |
| Total units | 109 |
| Buildings | 1 |
| Land | 0.7 acres |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 0% | 86 |
"—" means MahaRERA shows no figure for that update.
Other phases of this project
About this project
Destination Ostia Bldg H1 and Commercial Bldg 2 (MahaRERA P52100027455) is a residential project by D R Gavhane Landmarks LLP in Charholi, Pune 412105. It was launched in December 2020. It has 109 units in 1 building: 96 homes (2 & 3 BHK) and 13 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in December 2024. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes not started. MahaRERA records do not show it as ready to move in.
86 of its 109 units are booked (79%).
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.