Silicon BAY, Vadgaon Sheri

Lapsed

by Karan Janhavi Development Coroporation. Vadgaon Sheri, Pune 411014. View on Google Maps

Launched
First of 2 phases
Possession dates (MahaRERA)
Jan 2024No phase has an extended possession date. What does Lapsed mean?
Concrete structure (RCC)
100%Nearing possession2 of 2 phases with structure completeWeighted across 2 phases
Units booked
71 of 9575% booked
Price per sq ft
₹9,2002023 salesSee what buyers paid

Project facts

2 BHK49
3 BHK46
Total units95
Buildings2
Land1.5 acres
Phases2
MahaRERA complaints (filed by or against the builder)0
Share on WhatsApp

Shortlist 2 or more to compare side by side.

What buyers paid here

From government sale records

What buyers paid in registered sales, not today's asking price. Use it to compare projects, then ask the builder for the current rate.

Flat types, sizes and prices

Flat typeSize (total internal area)What most buyers paidYear
3 BHKabout 910 sq ft₹83 lakh2023 sales

Price per sq ft, year by year

2023₹9,200 per sq ft

Registered sales across all 2 phases.

Compared with the typical Vadgaon Sheri rate in 2023: about 25% lower

How to read this price
  • 80% of registered sales that year were at this rate or less.
  • Size is total internal area: carpet + balcony + terrace.
  • Higher floors, corner flats and open views usually cost more; lower floors and road-facing flats often less.
  • The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.
  • Fewer sales means a less certain figure.
  • Use it as a starting point for questions, not as an offer price.

Why this rate differs from other websites

The 2 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Silicon BAY Phase II
Ready to move Lapsed
P5210002785047100%85%
Silicon BAY Phase III
Completed
P5210003216348100%65%
Show updates by phase

Silicon BAY Phase II (P52100027850)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%95%40

"—" means MahaRERA shows no figure for that update.

Silicon BAY Phase III (P52100032163)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%14%10%31

"—" means MahaRERA shows no figure for that update.

How to read construction stages
Early stage
The concrete structure (RCC) has not started yet.
Mid-construction
The concrete structure (RCC) is being built.
Nearing possession
The concrete structure (RCC) is complete and final finishes are below 90%.
Ready to move
MahaRERA shows the project Completed, or the concrete structure (RCC) is complete and final finishes are 90% or more.
Concrete structure (RCC)
The reinforced-concrete frame of the building: columns, beams and slabs.
Final finishes
Lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
Lapsed
MahaRERA status when the possession date has passed with no extension or completion filed; it does not by itself mean work has stopped.

How to read construction stages

About this project

Silicon BAY is a project by Karan Janhavi Development Coroporation in Vadgaon Sheri, Pune 411014, registered with MahaRERA as 2 phases (P52100027850, P52100032163). The first phase was launched in January 2021. Together the phases have 95 units in 2 buildings, with 2 & 3 BHK homes as registered with MahaRERA. On MahaRERA, 1 is lapsed and 1 is completed.

The registered possession date is January 2024; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 100% complete and final finishes 52% complete. 2 of the 2 phases have their structure complete.

71 of the 95 units reported for sale are booked (75%). In 2023 registered sales, 80% of flats here sold at ₹9,200 per sq ft or less, counting balconies and terrace in the size. Buyers here paid a rate about 25% lower than the typical Vadgaon Sheri rate in 2023. Most buyers paid ₹83 lakh for 3 BHK flats of about 910 sq ft (2023 sales). The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.

Source: MahaRERA registrations P52100027850 and P52100032163.Open MahaRERA and search P52100027850All projects in Kharadi, Vadgaon Sheri, Viman Nagar