Skip to main content
← Back

Arnav Dopioo, Autadwadi Handewadi

Finishing stageLapsed

Final finishes 100% · completion not yet filed on MahaRERA

by Dattatray Madhukar Bhangire. Autadwadi Handewadi, Pune 412308. View on Google Maps

Launched
3 years 5 months originally promised
Possession date (MahaRERA)
1 year 4 months ago. No further extension recordedExtended by 1 year (originally June 2024). What "Lapsed" means
Concrete structure (RCC)
100%Finishing stage
Units booked
98 of 12777% booked

Project facts

1 BHK50
2 BHK66
Other units (shops, offices or not given by type)11
Total units127
Buildings1
Land1 acre
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: booked 77 → 98 · structure 86% → 100% · final finishes 60% → 100%

Share on WhatsApp

Construction progress

As reported to MahaRERA at each update
Time used and structure built
All of the originally promised 3 years 5 months have passed
Concrete structure (RCC) 100% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 0%Jun 2024: Excavation 50%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 0%Jun 2024: Concrete structure (RCC) 50%Dec 2024: Concrete structure (RCC) 100%Jun 2025: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 86%Jul 2026: Concrete structure (RCC) 100%Dec 2023: Final finishes 0%Jun 2024: Final finishes 25%Dec 2024: Final finishes 50%Jun 2025: Final finishes 50%Dec 2025: Final finishes 60%Jul 2026: Final finishes 100%Excavation 100%Concrete structure (RCC) 100%Final finishes 100%

If a percentage drops between updates, we show it as MahaRERA reported it.

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%98
100%86%60%77
100%100%50%52
50%50%25%44
0%0%0%21

"—" means MahaRERA shows no figure for that update.

About this project

Arnav Dopioo (MahaRERA P52100027985) is a residential project by Dattatray Madhukar Bhangire in Autadwadi Handewadi, Pune 412308. It was launched in January 2021. It has 127 units in 1 building: 116 homes (1 & 2 BHK) and 11 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in June 2025, after an extension of 1 year from the original June 2024. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete (structure and final finishes), but completion has not yet been recorded on MahaRERA.

98 of its 127 units are booked (77%). Since the December 2025 update, 21 more units have been booked and the reported concrete structure (RCC) has gone from 86% to 100%.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100027985.Check it on MahaRERA (P52100027985)All projects in Phursungi