- Launched
- 5 years 4 months promised
- Possession date (MahaRERA)
- 4 months ago. No extension recordedPossession date unchanged since launch. What "Lapsed" means
- Concrete structure (RCC)
- 100%Nearing possessionAverage across 3 buildings
- Units booked
- 128 of 17972% booked
Project facts
| 1 BHK | 179 |
|---|---|
| Total units | 179 |
| Buildings | 3 |
| Land | 1.9 acres |
| Reserved units | 30 |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Since Dec 2025: booked 96 → 128 · final finishes 10% → 50% · total units 180 → 179
Compared with 3 similar projects in PIN 412114
Projects with 80–400 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 5 yrs 4 mths | 4 yrs 2 mths |
| Possession date extended | No | 2 of 3 |
| Possession date passed | Yes, due June 2026 | 2 ready to move; 0 also past their date |
| Concrete structure (RCC) complete | 100% | 100% |
| Share of units booked | 72% | 88% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Ganesh Siddhi E Wing | October 2021 | December 2026 | 40% | 31 of 156 booked (20%) |
| Blue Dice Phase III | October 2021 | March 2025 | 100% | 87 of 93 booked (94%) |
| Adhya Radhakrishna C Wing | November 2021 | October 2026 | 100% | 78 of 89 booked (88%) |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 50% | 128 | |
| 100% | 100% | 10% | 96 | |
| 0% | 0% | 0% | 158 |
"—" means MahaRERA shows no figure for that update.
About this project
Silver 18 (MahaRERA P52100028139) is a residential project by Mayuresh Infra in Chikhali, Pune 412114. It was launched in February 2021. It has 179 units in 3 buildings, with 1 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in June 2026. That date has passed and no extension has been recorded. Construction, averaged across its 3 buildings: excavation complete, structure (RCC) complete, final finishes 50% complete. MahaRERA records do not show it as ready to move in.
128 of its 179 units are booked (72%). Since the December 2025 update, 32 more units have been booked.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.