Skip to main content
← Back

Shree Chinar Cooperative Society Limited, Kothrud

Finishing stageLapsed

Final finishes 95% · completion not yet filed on MahaRERA

by Saachee Infra. Kothrud, Pune 411029. View on Google Maps

Launched
3 years 5 months originally promised
Possession date (MahaRERA)
1 year 4 months ago. No further extension recordedExtended by 11 months (originally July 2024). What "Lapsed" means
Concrete structure (RCC)
100%Finishing stage
Units booked
11 of 5420% booked

Project facts

1 BHK11
2 BHK25
3 BHK12
4 BHK1
Other units (shops, offices or not given by type)5
Total units54
Buildings1
Land0.3 acres
Landowner share32
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: final finishes 80% → 95%

Share on WhatsApp

Construction progress

As reported to MahaRERA at each update
Time used and structure built
All of the originally promised 3 years 5 months have passed
Concrete structure (RCC) 100% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 100%Jun 2024: Excavation 100%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 90%Jun 2024: Concrete structure (RCC) 90%Dec 2024: Concrete structure (RCC) 85%Jun 2025: Concrete structure (RCC) 85%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2023: Final finishes 0%Jun 2024: Final finishes 0%Dec 2024: Final finishes 10%Jun 2025: Final finishes 10%Dec 2025: Final finishes 80%Jul 2026: Final finishes 95%Excavation 100%Concrete structure (RCC) 100%Final finishes 95%

If a percentage drops between updates, we show it as MahaRERA reported it.

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%95%11
100%100%80%11
100%85%10%43
100%90%0%11
100%90%0%4

"—" means MahaRERA shows no figure for that update.

About this project

Shree Chinar Cooperative Society Limited (MahaRERA P52100028145) is a residential project by Saachee Infra in Kothrud, Pune 411029. It was launched in February 2021. It has 54 units in 1 building: 49 homes (1, 2, 3 & 4 BHK) and 5 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in June 2025, after an extension of 11 months from the original July 2024. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 95% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.

11 of its 54 units are booked (20%).

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100028145.Check it on MahaRERA (P52100028145)All projects in Kothrud