Asmi Pride, Bhukum
by M/S Icon Developers. Bhukum, Pune 412115. View on Google Maps
- Launched
- 4 years 4 months originally promised
- Possession date (MahaRERA)
- 2 months awayExtended by 1 year 6 months (originally June 2025). Why possession dates change
- Concrete structure (RCC)
- 93%Mid-constructionAverage across 3 buildings
- Units booked
- 114 of 16868% booked
Project facts
| 1 BHK | 120 |
|---|---|
| 2 BHK | 48 |
| Total units | 168 |
| Buildings | 3 |
| Land | 1.7 acres |
| Landowner share | 50 |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Since Dec 2025: booked 164 → 114 · possession date June 2025 → December 2026
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 93% | 83% | 114 | |
| 100% | 93% | 83% | 164 | |
| 100% | 80% | 67% | 141 | |
| 100% | 77% | 57% | 127 |
"—" means MahaRERA shows no figure for that update.
About this project
Asmi Pride (MahaRERA P52100028299) is a residential project by M/S Icon Developers in Bhukum, Pune 412115. It was launched in February 2021. It has 168 units in 3 buildings, with 1 & 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2026, extended by 1 year 6 months from the original June 2025. Construction, averaged across its 3 buildings: excavation complete, structure (RCC) 93% complete, final finishes 83% complete. MahaRERA records do not show it as ready to move in.
114 of its 168 units are booked (68%). Since the December 2025 update, the possession date has moved from June 2025 to December 2026.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.