Skip to main content
← Back

Joyville Hadapsar Annexe Phase 11, Shewalewadi

Lapsed

by Joyville Shapoorji Housing Private Limited. Shewalewadi, Pune 412307. View on Google Maps

Launched
4 years 11 months promised
Possession date (MahaRERA)
9 months ago. No extension recordedPossession date unchanged since launch. What "Lapsed" means
Concrete structure (RCC)
100%Nearing possession
Units booked
120 of 13291% booked

Project facts

1 BHK4
2 BHK128
Total units132
Buildings1
Land0.5 acres
Complaints on MahaRERA (filed by or against the builder)0
Share on WhatsApp

Construction progress

As reported to MahaRERA at each update
Time used and structure built
All of the promised 4 years 11 months have passed
Concrete structure (RCC) 100% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 100%Jun 2024: Excavation 100%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 57%Jun 2024: Concrete structure (RCC) 100%Dec 2024: Concrete structure (RCC) 100%Jun 2025: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2023: Final finishes 0%Jun 2024: Final finishes 13%Dec 2024: Final finishes 43%Jun 2025: Final finishes 43%Dec 2025: Final finishes 43%Jul 2026: Final finishes 43%Excavation 100%Concrete structure (RCC) 100%Final finishes 43%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%43%120
100%100%43%124
100%100%13%114
100%57%0%109

"—" means MahaRERA shows no figure for that update.

Other phases of this project

About this project

Joyville Hadapsar Annexe Phase 11 (MahaRERA P52100028311) is a residential project by Joyville Shapoorji Housing Private Limited in Shewalewadi, Pune 412307. It was launched in February 2021. It has 132 units in 1 building, with 1 & 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in January 2026. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 43% complete. MahaRERA records do not show it as ready to move in.

120 of its 132 units are booked (91%).

Shapoorji Pallonji's track record in Pune

MahaRERA projects registered 2017–2026, in the 59 areas FlatNama covers

Projects registered with MahaRERA52
Completed without extending the possession date18
Completed after an extension, or lapsed10
Under construction24
Possession date extended by the builder5
Typical time from launch to 100% structure3 years 4 months
Complaints on MahaRERA, all Shapoorji Pallonji projects22 (15 of 52 projects)

See all Shapoorji Pallonji projects →

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100028311.Check it on MahaRERA (P52100028311)All projects in Manjari, Shewalewadi