Ekdant Hights, Pimple Saudagar
by Xpanz Buildcon. Pimple Saudagar, Pune 411027. View on Google Maps
- Launched
- 3 years 10 months originally promised
- Possession date (MahaRERA)
- 1 year 2 months awayExtended by 3 years (originally December 2024). Why possession dates change
- Concrete structure (RCC)
- 80%Mid-construction
- Units booked
- 8 of 3821% booked
Project facts
| 1 BHK | 4 |
|---|---|
| 2 BHK | 18 |
| Other units (shops, offices or not given by type) | 16 |
| Total units | 38 |
| Buildings | 1 |
| Land | 0.2 acres |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Construction progress
As reported to MahaRERA at each updateConcrete structure (RCC)Final finishesExcavation
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 80% | 0% | 8 | |
| 100% | 70% | 0% | 6 | |
| 100% | 30% | 0% | — |
"—" means MahaRERA shows no figure for that update.
About this project
Ekdant Hights (MahaRERA P52100028356) is a residential project by Xpanz Buildcon in Pimple Saudagar, Pune 411027. It was launched in February 2021. It has 38 units in 1 building: 22 homes (1 & 2 BHK) and 16 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2027, extended by 3 years from the original December 2024. Construction: excavation complete, structure (RCC) 80% complete, final finishes not started. MahaRERA records do not show it as ready to move in.
8 of its 38 units are booked (21%).
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.
Source: MahaRERA registration P52100028356.Check it on MahaRERA (P52100028356)All projects in Pimple Saudagar, Pimple Nilakh