Guardian Cityscapes Phase-3, Parvati

Finishing stageLapsed

Final finishes 93% · completion not yet filed on MahaRERA

by Guardian Homes Private Limited. Parvati, Pune 411030. View on Google Maps

Launched
4 years 3 months originally promised
Possession date (MahaRERA)
4 months ago. No further extension recordedExtended by 1 year (originally June 2025). What "Lapsed" means
Concrete structure (RCC)
100%Finishing stageAverage across 2 buildings
Units booked
152 of 15499% booked

Project facts

2 BHK95
3 BHK57
Other units (shops, offices or not given by type)2
Total units154
Buildings2
Land1.5 acres
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: booked 150 → 152

Share on WhatsApp

Construction progress

As reported to MahaRERA at each update
Time used and structure built
All of the originally promised 4 years 3 months have passed
Concrete structure (RCC) 100% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 100%Jun 2024: Excavation 100%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 100%Jun 2024: Concrete structure (RCC) 100%Dec 2024: Concrete structure (RCC) 100%Jun 2025: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2023: Final finishes 40%Jun 2024: Final finishes 75%Dec 2024: Final finishes 75%Jun 2025: Final finishes 75%Dec 2025: Final finishes 93%Jul 2026: Final finishes 93%Excavation 100%Concrete structure (RCC) 100%Final finishes 93%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%93%152
100%100%93%150
100%100%75%132
100%100%40%8

"—" means MahaRERA shows no figure for that update.

Other phases of this project

About this project

Guardian Cityscapes Phase-3 (MahaRERA P52100028630) is a residential project by Guardian Homes Private Limited in Parvati, Pune 411030. It was launched in March 2021. It has 154 units in 2 buildings: 152 homes (2 & 3 BHK) and 2 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in June 2026, after an extension of 1 year from the original June 2025. That date has passed and no further extension has been recorded. Construction, averaged across its 2 buildings: excavation complete, structure (RCC) complete, final finishes 93% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.

152 of its 154 units are booked (99%). Since the December 2025 update, 2 more units have been booked.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100028630.Check it on MahaRERA (P52100028630)All projects in Sadashiv Peth, Parvati