The Collection - W2 and W7, Vadgaon Sheri
by Bramhacorp Limited. Vadgaon Sheri, Pune 411014. View on Google Maps
- Launched
- 5 years 6 months promised
- Possession date (MahaRERA)
- 1 month agoPossession date unchanged since launch
- Concrete structure (RCC)
- 100%Nearing possessionAverage across 3 buildings
- Units booked
- 289 of 33886% booked
- Price per sq ft (incl. balconies and terrace)
- ₹13,6002025 · 12 salesabout the same as 202480% of the 2025 sales we found were at this rate or lessSee what buyers paid
Project facts
| 2 BHK | 60 |
|---|---|
| 3 BHK | 136 |
| 4 BHK | 98 |
| 5+ BHK | 5 |
| Other units (shops, offices or not given by type) | 39 |
| Total units | 338 |
| Buildings | 3 |
| Land | 0.4 acres |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Since Dec 2025: booked 288 → 289 · final finishes 75% → 83%
What buyers paid here
From government sale recordsThe price per sq ft is the agreed price of the flat alone, counting balconies and terrace.
Price per sq ft, year by year
80% of the flats sold in each year went for this price or less.
| 2024 | ₹13,600 per sq ft | 13 sales |
|---|---|---|
| 2025about the same as 2024 | ₹13,600 per sq ft | 12 sales |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 83% | 289 | |
| 100% | 100% | 75% | 288 | |
| 100% | 100% | 22% | 275 | |
| 100% | 98% | 3% | 273 | |
| 100% | 79% | 0% | 256 |
"—" means MahaRERA shows no figure for that update.
Other phases of this project
About this project
The Collection - W2 and W7 (MahaRERA P52100028754) is a residential project by Bramhacorp Limited in Vadgaon Sheri, Pune 411014. It was launched in March 2021. It has 338 units in 3 buildings: 299 homes (2, 3, 4 & 5+ BHK) and 39 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is September 2026, unchanged since launch. Construction, averaged across its 3 buildings: excavation complete, structure (RCC) complete, final finishes 83% complete. MahaRERA records do not show it as ready to move in.
289 of its 338 units are booked (86%). Since the December 2025 update, 1 more unit has been booked. 80% of the 2025 sales we found here were at ₹13,600 per sq ft or less (about the same as 2024), counting balconies and terrace in the size, based on 12 registered sales.
Bramhacorp's track record in Pune
MahaRERA projects registered 2017–2026, in the 59 areas FlatNama covers
| Projects registered with MahaRERA | 15 |
|---|---|
| Completed without extending the possession date | 4 |
| Completed after an extension, or lapsed | 0 |
| Under construction | 11 |
| Possession date extended by the builder | 0 |
| Typical time from launch to 100% structure | 3 years 2 months |
| Complaints on MahaRERA, all Bramhacorp projects | 3 (3 of 15 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not extend its possession date. MahaRERA's COVID extensions (6 + 6 months, 2020–21) are not counted as the builder's.
- Completed after an extension, or lapsed: every other registration that is not under construction.
- Under construction: MahaRERA status Active.
- Possession date extended by the builder: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure reached 100% between December 2023 and July 2026, counted from registration.
- Complaints: complaints on MahaRERA filed by or against the builder, on all its projects.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.