Skip to main content
← Back

Laxmi Puram, Khadakwasla

by Vipul Construction. Khadakwasla, Pune 411024. View on Google Maps

Launched
3 years 10 months originally promised
Possession date (MahaRERA)
11 months awayExtended by 2 years 7 months (originally February 2025). Why possession dates change
Concrete structure (RCC)
33%Mid-constructionAverage across 2 buildings
Units booked
4 of 4010% booked

Project facts

1 BHK36
2 BHK4
Total units40
Buildings2
Land0.3 acres
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: structure 43% → 33%

Share on WhatsApp

Construction progress

As reported to MahaRERA at each update
Time used and structure built
All of the originally promised 3 years 10 months have passed
Concrete structure (RCC) 33% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 40%Jun 2024: Excavation 40%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 5%Jun 2024: Concrete structure (RCC) 5%Dec 2024: Concrete structure (RCC) 60%Jun 2025: Concrete structure (RCC) 60%Dec 2025: Concrete structure (RCC) 43%Jul 2026: Concrete structure (RCC) 33%Dec 2023: Final finishes 25%Jun 2024: Final finishes 25%Dec 2024: Final finishes 25%Jun 2025: Final finishes 25%Dec 2025: Final finishes 20%Jul 2026: Final finishes 20%Excavation 100%Concrete structure (RCC) 33%Final finishes 20%

If a percentage drops between updates, we show it as MahaRERA reported it.

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%33%20%4
100%43%20%4
100%60%25%1
40%5%25%1

"—" means MahaRERA shows no figure for that update.

About this project

Laxmi Puram (MahaRERA P52100028932) is a residential project by Vipul Construction in Khadakwasla, Pune 411024. It was launched in April 2021. It has 40 units in 2 buildings, with 1 & 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is September 2027, extended by 2 years 7 months from the original February 2025. Construction, averaged across its 2 buildings: excavation complete, structure (RCC) 33% complete, final finishes 20% complete. MahaRERA records do not show it as ready to move in.

4 of its 40 units are booked (10%). Since the December 2025 update, the reported concrete structure (RCC) has gone from 43% to 33%.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100028932.Check it on MahaRERA (P52100028932)All projects in Khadakwasla, Kirkatwadi