Skip to main content
← Back

Sonchandr Residency, Maan

by Chandan Ramdas Kate. Maan, Pune 411057. View on Google Maps

Launched
11 months originally promised
Possession date (MahaRERA)
10 months ago. No further extension recordedExtended by 3 years 9 months (originally March 2022). Why possession dates change
Concrete structure (RCC)
100%Nearing possession
Units booked
12 of 3732% booked

Project facts

1 BHK12
2 BHK12
Other units (shops, offices or not given by type)13
Total units37
Buildings1
Land0.6 acres
Complaints on MahaRERA (filed by or against the builder)0
Share on WhatsApp

Construction progress

As reported to MahaRERA at each update
Time used and structure built
All of the originally promised 11 months have passed
Concrete structure (RCC) 100% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 0%Jun 2024: Excavation 100%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 0%Jun 2024: Concrete structure (RCC) 100%Dec 2024: Concrete structure (RCC) 100%Jun 2025: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2023: Final finishes 0%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 100%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%0%12
100%100%0%5
0%0%0%5

"—" means MahaRERA shows no figure for that update.

About this project

Sonchandr Residency (MahaRERA P52100029069) is a residential project by Chandan Ramdas Kate in Maan, Pune 411057. It was launched in April 2021. It has 37 units in 1 building: 24 homes (1 & 2 BHK) and 13 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Possession was due in December 2025, after an extension of 3 years 9 months from the original March 2022. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes not started. MahaRERA records do not show it as ready to move in.

12 of its 37 units are booked (32%).

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100029069.Check it on MahaRERA (P52100029069)All projects in Wakad, Hinjewadi, Marunji