Puneville, Punawale

by Benchmarrk Realty Pvt. Ltd.. Punawale, Pune 411033. View on Google Maps

Launched
First of 4 phases
Possession dates (MahaRERA)
Jun 2028 – Mar 2031varies by phaseNo phase has an extended possession date
Concrete structure (RCC)
39%Mid-construction0 of 4 phases with structure completeWeighted across 4 phases
Units booked
589 of 89766% booked
Price per sq ft
₹9,5002026 salesup 4% on 2025See what buyers paid

Project facts

2 BHK514
3 BHK383
Total units897
Buildings8
Land3.6 acres
Phases4
MahaRERA complaints (filed by or against the builder)21
Share on WhatsApp

Shortlist 2 or more to compare side by side.

What buyers paid here

From government sale records

What buyers paid in registered sales, not today's asking price. Use it to compare projects, then ask the builder for the current rate.

Flat types, sizes and prices

Flat typeSize (total internal area)What most buyers paidYear
2 BHKabout 730 – 860 sq ft₹72 – 83 lakh2026 sales
3 BHKabout 1,160 sq ft₹89 lakh – ₹1.13 crore2026 sales

Price per sq ft, year by year

2023₹8,000 per sq ft
2024up 6% on 2023₹8,500 per sq ft
2025up 7% on 2024₹9,100 per sq ft
2026up 4% on 2025₹9,500 per sq ft

Registered sales across all 4 phases.

Compared with the typical Punawale rate in 2026: about 10% lower

How to read this price
  • 80% of registered sales that year were at this rate or less.
  • Size is total internal area: carpet + balcony + terrace.
  • Higher floors, corner flats and open views usually cost more; lower floors and road-facing flats often less.
  • The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.
  • Fewer sales means a less certain figure.
  • Use it as a starting point for questions, not as an offer price.

Why this rate differs from other websites

The 4 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Puneville Phase III Cluster A
Mid-construction
P5210002952221478%71%
Puneville Phase III Cluster B
Mid-construction
P5210004769421479%57%
Puneville Phase III Cluster C
Mid-construction
P5210005102010414%91%
Puneville Phase III Cluster D
Mid-construction
P521000774313651%61%
Show updates by phase

Puneville Phase III Cluster A (P52100029522)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%78%0%152
100%73%0%151
100%60%0%146
100%30%0%133

"—" means MahaRERA shows no figure for that update.

Puneville Phase III Cluster B (P52100047694)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%79%0%121
100%69%0%115
100%49%0%110
100%15%0%61

"—" means MahaRERA shows no figure for that update.

Puneville Phase III Cluster C (P52100051020)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%14%0%95
100%7%0%94
100%0%0%67
100%0%0%16

"—" means MahaRERA shows no figure for that update.

Puneville Phase III Cluster D (P52100077431)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
67%1%0%221
67%0%0%104

"—" means MahaRERA shows no figure for that update.

How to read construction stages
Early stage
The concrete structure (RCC) has not started yet.
Mid-construction
The concrete structure (RCC) is being built.
Nearing possession
The concrete structure (RCC) is complete and final finishes are below 90%.
Ready to move
MahaRERA shows the project Completed, or the concrete structure (RCC) is complete and final finishes are 90% or more.
Concrete structure (RCC)
The reinforced-concrete frame of the building: columns, beams and slabs.
Final finishes
Lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
Lapsed
MahaRERA status when the possession date has passed with no extension or completion filed; it does not by itself mean work has stopped.

How to read construction stages

About this project

Puneville is a project by Benchmarrk Realty Pvt. Ltd. in Punawale, Pune 411033, registered with MahaRERA as 4 phases (P52100029522, P52100047694, P52100051020, P52100077431). The first phase was launched in June 2021. Together the phases have 897 units in 8 buildings, with 2 & 3 BHK homes as registered with MahaRERA. All 4 phases are active on MahaRERA.

The phases' registered possession dates run from June 2028 to March 2031; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 39% complete and final finishes 0% complete. 0 of the 4 phases have their structure complete.

589 of the 897 units reported for sale are booked (66%). In 2026 registered sales, 80% of flats here sold at ₹9,500 per sq ft or less (up 4% on 2025), counting balconies and terrace in the size. Buyers here paid a rate about 10% lower than the typical Punawale rate in 2026. Most buyers paid ₹72–83 lakh for 2 BHK flats of about 730–860 sq ft (2026 sales); ₹89 lakh–₹1.13 crore for 3 BHK flats of about 1,160 sq ft (2026 sales). The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.

Pharande's track record in Pune

MahaRERA projects registered 2017–2026 in Pune & PCMC

Projects registered with MahaRERA28
Completed without extending the possession date5
Completed after an extension2
Lapsed5
Under construction16
Possession date extended on the builder's application5
Typical time from launch to 100% structure3 years 1 month
MahaRERA complaints (filed by or against the builder), all Pharande projects32 (7 of 28 projects)

See all Pharande projects →

Source: MahaRERA registrations P52100029522, P52100047694, P52100051020 and P52100077431.Open MahaRERA and search P52100029522All projects in Tathawade, Punawale, Jambhe