Skip to main content
← Back

Vivaan Park, Lohegaon

by Shriram Associates. Lohegaon, Pune 411047. View on Google Maps

Launched
5 years 5 months promised
Possession date (MahaRERA)
2 months awayPossession date unchanged since launch
Concrete structure (RCC)
98%Mid-constructionAverage across 4 buildings
Units booked
137 of 24755% booked

Project facts

2 BHK157
3 BHK64
Other units (shops, offices or not given by type)26
Total units247
Buildings4
Land2 acres
Landowner share46
Complaints on MahaRERA (filed by or against the builder)0
Share on WhatsApp

Compared with 4 similar projects in PIN 411047

Projects with 100–450 flats, launched within 1 year of this one.

Compared with 4 similar projects in PIN 411047
MeasureThis projectSimilar projects
Promised timeline (launch to possession)5 yrs 5 mths3 yrs
Possession date extendedNo3 of 4
Possession date (MahaRERA)December 2026July 2027
Concrete structure (RCC) complete98%90%
Share of units booked55%39%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
5 years 3 months of the promised 5 years 5 months have passed
Concrete structure (RCC) 98% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 50%Jun 2024: Excavation 50%Dec 2024: Excavation 50%Jun 2025: Excavation 50%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 0%Jun 2024: Concrete structure (RCC) 0%Dec 2024: Concrete structure (RCC) 0%Jun 2025: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 98%Jul 2026: Concrete structure (RCC) 98%Dec 2023: Final finishes 0%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 50%Jul 2026: Final finishes 50%Excavation 100%Concrete structure (RCC) 98%Final finishes 50%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%98%50%137
50%0%0%103
50%0%0%47

"—" means MahaRERA shows no figure for that update.

About this project

Vivaan Park (MahaRERA P52100029803) is a residential project by Shriram Associates in Lohegaon, Pune 411047. It was launched in July 2021. It has 247 units in 4 buildings: 221 homes (2 & 3 BHK) and 26 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2026, unchanged since launch. Construction, averaged across its 4 buildings: excavation complete, structure (RCC) 98% complete, final finishes 50% complete. MahaRERA records do not show it as ready to move in.

137 of its 247 units are booked (55%).

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100029803.Check it on MahaRERA (P52100029803)All projects in Lohegaon