Nivasa Enchante - Phase I, Lohegaon
Finishing stageLapsed
Final finishes 100% · completion not yet filed on MahaRERA
by Nivasa Associates. Lohegaon, Pune 411047. View on Google Maps
- Launched
- 3 years 11 months promised
- Possession date (MahaRERA)
- 7 months ago. No extension recordedPossession date unchanged since launch. What "Lapsed" means
- Concrete structure (RCC)
- 100%Finishing stageAverage across 4 buildings
- Units booked
- 263 of 28493% booked
Project facts
| 1 BHK | 4 |
|---|---|
| 2 BHK | 148 |
| 3 BHK | 132 |
| Total units | 284 |
| Buildings | 4 |
| Land | 1.7 acres |
| Complaints on MahaRERA (filed by or against the builder) | 1 |
Since Dec 2025: final finishes 30% → 100%
Compared with 3 similar projects in PIN 411047
Projects with 100–600 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 3 yrs 11 mths | 3 yrs 11 mths |
| Possession date extended | No | 1 of 3 |
| Possession date passed | Yes, due March 2026 | 0 ready to move; 1 also past their date |
| Concrete structure (RCC) complete | 100% | 85% |
| Share of units booked | 93% | 49% |
| Complaints on MahaRERA (filed by or against the builder) | 1 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Skyways Horizon | April 2022 | December 2025 | 80% | 106 of 215 booked (49%) |
| Divine Garden Phase 1 | January 2023 | December 2026 | 85% | 88 of 296 booked (30%) |
| Vivaan Park | July 2021 | December 2026 | 98% | 137 of 247 booked (55%) |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 263 | |
| 100% | 100% | 30% | 263 | |
| 100% | 100% | 10% | 195 | |
| 100% | 35% | 0% | 195 |
"—" means MahaRERA shows no figure for that update.
Other phases of this project
About this project
Nivasa Enchante - Phase I (MahaRERA P52100034898) is a residential project by Nivasa Associates in Lohegaon, Pune 411047. It was launched in April 2022. It has 284 units in 4 buildings, with 1, 2 & 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in March 2026. That date has passed and no extension has been recorded. Construction, averaged across its 4 buildings: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete (structure and final finishes), but completion has not yet been recorded on MahaRERA.
263 of its 284 units are booked (93%).
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.