Shlok, Borhadewadi

by Vrunda Ventures LLP. Borhadewadi, Pune 412105. View on Google Maps

Launched
5 years 5 months promised
Possession date (MahaRERA)
2 months awayPossession date unchanged since launch
Concrete structure (RCC)
67%Mid-constructionAverage across 3 buildings
Units booked
299 of 32791% booked

Project facts

2 BHK197
3 BHK98
Other units (shops, offices or not given by type)32
Total units327
Buildings3
Land2.1 acres
Complaints on MahaRERA (filed by or against the builder)8

Since Dec 2025: booked 286 → 299 · final finishes 33% → 53% · complaints 4 → 8

Share on WhatsApp

Compared with 4 similar projects in PIN 412105

Projects with 100–600 flats, launched within 6 months of this one.

Compared with 4 similar projects in PIN 412105
MeasureThis projectSimilar projects
Promised timeline (launch to possession)5 yrs 5 mths3 yrs 10 mths
Possession date extendedNo3 of 4
Possession date (MahaRERA)December 2026September 2026
Concrete structure (RCC) complete67%100%
Share of units booked91%72%
Complaints on MahaRERA (filed by or against the builder)80

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
5 years 3 months of the promised 5 years 5 months have passed
Concrete structure (RCC) 67% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 47%Jun 2024: Excavation 73%Dec 2024: Excavation 73%Jun 2025: Excavation 73%Dec 2025: Excavation 67%Jul 2026: Excavation 67%Dec 2023: Concrete structure (RCC) 8%Jun 2024: Concrete structure (RCC) 33%Dec 2024: Concrete structure (RCC) 48%Jun 2025: Concrete structure (RCC) 48%Dec 2025: Concrete structure (RCC) 67%Jul 2026: Concrete structure (RCC) 67%Dec 2023: Final finishes 0%Jun 2024: Final finishes 17%Dec 2024: Final finishes 28%Jun 2025: Final finishes 28%Dec 2025: Final finishes 33%Jul 2026: Final finishes 53%Excavation 67%Concrete structure (RCC) 67%Final finishes 53%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
67%67%53%299
67%67%33%286
73%48%28%254
73%33%17%222
47%8%0%161

"—" means MahaRERA shows no figure for that update.

About this project

Shlok (MahaRERA P52100029815) is a residential project by Vrunda Ventures LLP in Borhadewadi, Pune 412105. It was launched in July 2021. It has 327 units in 3 buildings: 295 homes (2 & 3 BHK) and 32 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2026, unchanged since launch. Construction, averaged across its 3 buildings: excavation 67% complete, structure (RCC) 67% complete, final finishes 53% complete. MahaRERA records do not show it as ready to move in.

299 of its 327 units are booked (91%). Since the December 2025 update, 13 more units have been booked.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100029815.Check it on MahaRERA (P52100029815)All projects in Charholi, Moshi