Swastik Twin Tower, Charholi
Finishing stage
Final finishes 100% · completion not yet filed on MahaRERA
by Swastik Builders. Charholi, Pune 412105. View on Google Maps
- Launched
- 5 years promised
- Possession date (MahaRERA)
- 3 months agoPossession date unchanged since launch
- Concrete structure (RCC)
- 100%Finishing stageAverage across 2 buildings
- Units booked
- 180 of 25172% booked
Project facts
| 1 BHK | 58 |
|---|---|
| 2 BHK | 169 |
| 3 BHK | 13 |
| Other units (shops, offices or not given by type) | 11 |
| Total units | 251 |
| Buildings | 2 |
| Land | 1.3 acres |
| Landowner share | 58 |
| Reserved units | 13 |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Since Dec 2025: booked 107 → 180 · structure 65% → 100% · final finishes 0% → 100%
Compared with 6 similar projects in PIN 412105
Projects with 100–500 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 5 yrs | 3 yrs 8 mths |
| Possession date extended | No | 5 of 6 |
| Possession date (MahaRERA) | July 2026 | December 2026 |
| Concrete structure (RCC) complete | 100% | 100% |
| Share of units booked | 72% | 74% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 1 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Shlok | July 2021 | December 2026 | 67% | 299 of 327 booked (91%) |
| Onella Tower | July 2021 | May 2025 | 100% | 81 of 113 booked (72%) |
| Bliss County Phase I | May 2021 | December 2024 | 100% | 92 of 126 booked (73%) |
| Kamalraj Dattavihar E and H | November 2021 | December 2025 | 100% | 199 of 224 booked (89%) |
| Ideal Avenue | January 2021 | September 2025 | 100% | 116 of 154 booked (75%) |
| Dwaarka World PH 1 | January 2022 | December 2026 | 100% | 248 of 497 booked (50%) |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 180 | |
| 100% | 65% | 0% | 107 | |
| 100% | 3% | 0% | — |
"—" means MahaRERA shows no figure for that update.
About this project
Swastik Twin Tower (MahaRERA P52100030108) is a residential project by Swastik Builders in Charholi, Pune 412105. It was launched in July 2021. It has 251 units in 2 buildings: 240 homes (1, 2 & 3 BHK) and 11 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is July 2026, unchanged since launch. Construction, averaged across its 2 buildings: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete (structure and final finishes), but completion has not yet been recorded on MahaRERA.
180 of its 251 units are booked (72%). Since the December 2025 update, 73 more units have been booked and the reported concrete structure (RCC) has gone from 65% to 100%.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.