Mantra Meraki, Akurdi
by Mantra Residential Akurdi Private Limited. Akurdi, Pune 411035. View on Google Maps
- Launched
- First of 5 phases
- Possession dates (MahaRERA)
- Dec 2025 – Dec 2027varies by phase1 of 5 phases have an extended possession date. Reading a project's possession date
- Concrete structure (RCC)
- 93%Mid-construction4 of 5 phases with structure completeWeighted across 5 phases
- Units booked
- 362 of 362100% booked
Facts
Project facts
| 1 BHK | 43 |
|---|---|
| 2 BHK | 143 |
| 3 BHK | 168 |
| 4 BHK | 8 |
| Total units | 362 |
| Buildings | 5 |
| Land | 0.6 acres |
| Phases | 5 |
| MahaRERA complaints (filed by or against the builder) | 4 |
Since Dec 2025: booked 359 → 362
Shortlist 2 or more to compare side by side.
Phases
The 5 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| Mantra Meraki Phase 3 Ready to move Lapsed | P52100030518 | 86 | 100% | 100% | |
| Mantra Meraki Phase 2 Ready to move Lapsed | P52100030585 | 70 | 100% | 100% | |
| Mantra Meraki Phase 1 Ready to move Lapsed | P52100030605 | 86 | 100% | 100% | |
| Mantra Meraki Phase 7 Mid-construction | P52100034738 | 76 | 65% | 100% | |
| Mantra Meraki Phase 6 Nearing possession | P52100034965 | 44 | 100% | 100% |
Show updates by phase
Mantra Meraki Phase 3 (P52100030518)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 86 | |
| 100% | 100% | 95% | 86 | |
| 100% | 100% | 10% | 86 | |
| 100% | 91% | 0% | 85 | |
| 100% | 14% | 0% | 72 |
"—" means MahaRERA shows no figure for that update.
Mantra Meraki Phase 2 (P52100030585)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 70 | |
| 100% | 100% | 95% | 70 | |
| 100% | 100% | 10% | 69 | |
| 100% | 91% | 0% | 68 | |
| 100% | 22% | 0% | 54 |
"—" means MahaRERA shows no figure for that update.
Mantra Meraki Phase 1 (P52100030605)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 86 | |
| 100% | 100% | 95% | 86 | |
| 100% | 100% | 10% | 86 | |
| 100% | 91% | 0% | 86 | |
| 100% | 27% | 0% | 77 |
"—" means MahaRERA shows no figure for that update.
Mantra Meraki Phase 7 (P52100034738)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 65% | 0% | 76 | |
| 100% | 35% | 0% | 73 | |
| 100% | 26% | 0% | 73 | |
| 100% | 26% | 0% | 63 | |
| 95% | 0% | 0% | 52 |
"—" means MahaRERA shows no figure for that update.
Mantra Meraki Phase 6 (P52100034965)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 10% | 44 | |
| 100% | 80% | 0% | 44 | |
| 100% | 69% | 0% | 44 | |
| 100% | 52% | 0% | 44 | |
| 100% | 14% | 0% | 41 |
"—" means MahaRERA shows no figure for that update.
How to read construction stages
- Early stage
- The concrete structure (RCC) has not started yet.
- Mid-construction
- The concrete structure (RCC) is being built.
- Nearing possession
- The concrete structure (RCC) is complete and final finishes are below 90%.
- Ready to move
- MahaRERA shows the project Completed, or the concrete structure (RCC) is complete and final finishes are 90% or more.
- Concrete structure (RCC)
- The reinforced-concrete frame of the building: columns, beams and slabs.
- Final finishes
- Lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- Lapsed
- MahaRERA status when the possession date has passed with no extension or completion filed; it does not by itself mean work has stopped.
Other phases of this project
About this project
Mantra Meraki is a project by Mantra Residential Akurdi Private Limited in Akurdi, Pune 411035, registered with MahaRERA as 5 phases (P52100030518, P52100030585, P52100030605, P52100034738, P52100034965). The first phase was launched in August 2021. Together the phases have 362 units in 5 buildings, with 1, 2, 3 & 4 BHK homes as registered with MahaRERA. On MahaRERA, 3 are lapsed and 2 are active.
The phases' registered possession dates run from December 2025 to December 2027; 1 of 5 phases have an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 93% complete and final finishes 68% complete. 4 of the 5 phases have their structure complete.
362 of the 362 units reported for sale are booked (100%).
Mantra's track record in Pune
MahaRERA projects registered 2017–2026 in Pune & PCMC
| Projects registered with MahaRERA | 80 |
|---|---|
| Completed without extending the possession date | 41 |
| Completed after an extension | 5 |
| Lapsed | 11 |
| Under construction | 23 |
| Possession date extended on the builder's application | 7 |
| Typical time from launch to 100% structure | 2 years 10 months |
| MahaRERA complaints (filed by or against the builder), all Mantra projects | 58 (32 of 80 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and July 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.