Krystal One, Chikhali

by Rama Spaces. Chikhali, Pune 412114. View on Google Maps

Launched
First of 4 phases
Possession dates (MahaRERA)
Aug 2026 – Dec 2027varies by phase3 of 4 phases have an extended possession date. Reading a project's possession date
Concrete structure (RCC)
100%Nearing possession4 of 4 phases with structure completeWeighted across 4 phases
Units booked
646 of 71091% booked

Project facts

1 BHK16
2 BHK694
Total units710
Buildings6
Land1.3 acres
Phases4
MahaRERA complaints (filed by or against the builder)0

Since Dec 2025: booked 627 → 646

Share on WhatsApp

Shortlist 2 or more to compare side by side.

The 4 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Krystal One Phase I
Completed
P52100030567224100%100%
Krystal One Phase II
Ready to move
P52100047325112100%100%
Krystal One Phase III
Ready to move
P52100049781152100%100%
Krystal One Phase IV
Nearing possession
P52100055473222100%71%
Show updates by phase

Krystal One Phase I (P52100030567)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%224
100%100%25%224
100%100%0%224
100%97%0%224

"—" means MahaRERA shows no figure for that update.

Krystal One Phase II (P52100047325)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%112
100%100%0%112
100%100%0%107
100%56%0%95
100%0%0%74

"—" means MahaRERA shows no figure for that update.

Krystal One Phase III (P52100049781)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%152
100%100%0%152
100%100%0%97
100%70%0%67
100%0%0%38

"—" means MahaRERA shows no figure for that update.

Krystal One Phase IV (P52100055473)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%0%158
100%97%0%139
100%6%0%43
100%0%0%8

"—" means MahaRERA shows no figure for that update.

How to read construction stages
Early stage
The concrete structure (RCC) has not started yet.
Mid-construction
The concrete structure (RCC) is being built.
Nearing possession
The concrete structure (RCC) is complete and final finishes are below 90%.
Ready to move
MahaRERA shows the project Completed, or the concrete structure (RCC) is complete and final finishes are 90% or more.
Concrete structure (RCC)
The reinforced-concrete frame of the building: columns, beams and slabs.
Final finishes
Lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
Lapsed
MahaRERA status when the possession date has passed with no extension or completion filed; it does not by itself mean work has stopped.

How to read construction stages

About this project

Krystal One is a project by Rama Spaces in Chikhali, Pune 412114, registered with MahaRERA as 4 phases (P52100030567, P52100047325, P52100049781, P52100055473). The first phase was launched in September 2021. Together the phases have 710 units in 6 buildings, with 1 & 2 BHK homes as registered with MahaRERA. On MahaRERA, 3 are active and 1 is completed.

The phases' registered possession dates run from August 2026 to December 2027; 3 of 4 phases have an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 100% complete and final finishes 69% complete. 4 of the 4 phases have their structure complete.

646 of the 710 units reported for sale are booked (91%).

Source: MahaRERA registrations P52100030567, P52100047325, P52100049781 and P52100055473.Open MahaRERA and search P52100030567All projects in Chikhali, Talwade