Nexus Kinaara, Chikhali

by Nexus Enterprises. Chikhali, Pune 412114. View on Google Maps

Launched
First of 3 phases
Possession dates (MahaRERA)
Apr 20283 of 3 phases have an extended possession date. Reading a project's possession date
Concrete structure (RCC)
100%Nearing possession3 of 3 phases with structure completeWeighted across 3 phases
Units booked
372 of 53669% booked

Project facts

1 BHK15
2 BHK405
3 BHK116
Total units536
Buildings4
Land0.9 acres
Phases3
MahaRERA complaints (filed by or against the builder)0

Since Dec 2025: booked 330 → 372

Share on WhatsApp

Shortlist 2 or more to compare side by side.

The 3 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Nexus Kinaara B C
Completed
P52100031120236100%78%
Nexus Kinaara D
Completed
P52100033605120100%83%
Nexus Kinaara A
Nearing possession
P52100051339180100%49%
Show updates by phase

Nexus Kinaara B C (P52100031120)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%95%184
100%100%95%180
100%100%0%169
100%53%0%154

"—" means MahaRERA shows no figure for that update.

Nexus Kinaara D (P52100033605)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%95%99
100%100%0%92
100%41%0%36

"—" means MahaRERA shows no figure for that update.

Nexus Kinaara A (P52100051339)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%0%89
100%100%0%47
100%17%0%—

"—" means MahaRERA shows no figure for that update.

How to read construction stages
Early stage
The concrete structure (RCC) has not started yet.
Mid-construction
The concrete structure (RCC) is being built.
Nearing possession
The concrete structure (RCC) is complete and final finishes are below 90%.
Ready to move
MahaRERA shows the project Completed, or the concrete structure (RCC) is complete and final finishes are 90% or more.
Concrete structure (RCC)
The reinforced-concrete frame of the building: columns, beams and slabs.
Final finishes
Lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
Lapsed
MahaRERA status when the possession date has passed with no extension or completion filed; it does not by itself mean work has stopped.

How to read construction stages

About this project

Nexus Kinaara is a project by Nexus Enterprises in Chikhali, Pune 412114, registered with MahaRERA as 3 phases (P52100031120, P52100033605, P52100051339). The first phase was launched in October 2021. Together the phases have 536 units in 4 buildings, with 1, 2 & 3 BHK homes as registered with MahaRERA. On MahaRERA, 2 are completed and 1 is active.

The registered possession date is April 2028; 3 of 3 phases have an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 100% complete and final finishes 63% complete. 3 of the 3 phases have their structure complete.

372 of the 536 units reported for sale are booked (69%).

Source: MahaRERA registrations P52100031120, P52100033605 and P52100051339.Open MahaRERA and search P52100031120All projects in Chikhali, Talwade