Pawar Riseonic, Mundhwa

by Pawar Buildcon and Company. Mundhwa, Pune 411036. View on Google Maps

Launched
3 years originally promised
Possession date (MahaRERA)
9 months awayExtended by 2 years 9 months (originally October 2024). Why possession dates change
Concrete structure (RCC)
89%Mid-constructionAverage across 2 buildings
Units booked
69 of 12854% booked

Project facts

1 BHK4
2 BHK104
Other units (shops, offices or not given by type)20
Total units128
Buildings2
Land1 acre
Landowner share35
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: booked 65 → 69 · structure 75% → 89% · total units 95 → 128

Share on WhatsApp

Compared with 3 similar projects in PIN 411036

Projects with 50–250 flats, launched within 1 year of this one.

Compared with 3 similar projects in PIN 411036
MeasureThis projectSimilar projects
Promised timeline (launch to possession)3 yrs4 yrs 6 mths
Possession date extendedBy 2 years 9 months0 of 3
Possession date (MahaRERA)July 2027December 2026
Concrete structure (RCC) complete89%100%
Share of units booked54%100%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
All of the originally promised 3 years have passed
Concrete structure (RCC) 89% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 100%Jun 2024: Excavation 100%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 20%Jun 2024: Concrete structure (RCC) 20%Dec 2024: Concrete structure (RCC) 90%Jun 2025: Concrete structure (RCC) 90%Dec 2025: Concrete structure (RCC) 75%Jul 2026: Concrete structure (RCC) 89%Dec 2023: Final finishes 0%Jun 2024: Final finishes 0%Dec 2024: Final finishes 30%Jun 2025: Final finishes 30%Dec 2025: Final finishes 50%Jul 2026: Final finishes 50%Excavation 100%Concrete structure (RCC) 89%Final finishes 50%

If a percentage drops between updates, we show it as MahaRERA reported it.

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%89%50%69
100%75%50%65
100%90%30%44
100%20%0%32

"—" means MahaRERA shows no figure for that update.

About this project

Pawar Riseonic (MahaRERA P52100031525) is a residential project by Pawar Buildcon and Company in Mundhwa, Pune 411036. It was launched in October 2021. It has 128 units in 2 buildings: 108 homes (1 & 2 BHK) and 20 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is July 2027, extended by 2 years 9 months from the original October 2024. Construction, averaged across its 2 buildings: excavation complete, structure (RCC) 89% complete, final finishes 50% complete. MahaRERA records do not show it as ready to move in.

69 of its 128 units are booked (54%). Since the December 2025 update, 4 more units have been booked and the reported concrete structure (RCC) has gone from 75% to 89%.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100031525.Check it on MahaRERA (P52100031525)All projects in Mundhwa, Keshavnagar