VTP Euphoria, Manjari Khurd

by Ashdan Developers Private Limited. Manjari Khurd, Pune 412307. View on Google Maps

Launched
First of 5 phases
Possession dates (MahaRERA)
Dec 2026 – Dec 2028varies by phaseNo phase has an extended possession date
Concrete structure (RCC)
96%Mid-construction3 of 5 phases with structure completeWeighted across 5 phases
Units booked
1,872 of 2,03992% booked
Price per sq ft
₹11,7002026 salesup 4% on 2025See what buyers paid

Project facts

1 BHK294
2 BHK1,200
3 BHK598
Total units2,092
Buildings10
Land0.5 acres
Phases5
MahaRERA complaints (filed by or against the builder)72

Since Dec 2025: booked 1,784 → 1,872

Share on WhatsApp

Shortlist 2 or more to compare side by side.

What buyers paid here

From government sale records

What buyers paid in registered sales, not today's asking price. Use it to compare projects, then ask the builder for the current rate.

Flat types, sizes and prices

Flat typeSize (total internal area)What most buyers paidYear
1 RK / 1 BHKabout 460 sq ft₹42 – 48 lakh2024 sales
2 BHKabout 650 – 860 sq ft₹80 lakh – ₹1.00 crore2026 sales
3 BHKabout 1,150 – 1,240 sq ft₹1.34 – 1.47 crore2026 sales
4 BHKabout 1,450 – 2,050 sq ft₹1.17 – 1.48 crore2023 sales

Price per sq ft, year by year

2023₹9,100 per sq ft
2024up 16% on 2023₹10,600 per sq ft
2025up 6% on 2024₹11,200 per sq ft
2026up 4% on 2025₹11,700 per sq ft

Registered sales across all 5 phases.

Compared with the typical Manjari Khurd rate in 2026: similar

How to read this price
  • 80% of registered sales that year were at this rate or less.
  • Size is total internal area: carpet + balcony + terrace.
  • Higher floors, corner flats and open views usually cost more; lower floors and road-facing flats often less.
  • The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.
  • Fewer sales means a less certain figure.
  • Use it as a starting point for questions, not as an offer price.

Why this rate differs from other websites

The 5 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
VTP Euphoria Phase 1
Nearing possession
P52100031691594100%98%
VTP Euphoria Phase 2
Mid-construction
P5210004584836098%99%
VTP Euphoria Phase 3
Nearing possession
P52100047312718100%94%
VTP Euphoria Phase 4
Nearing possession
P52100049849240100%82%
VTP Euphoria Phase 5
Mid-construction
P5210007763718057%36%
Show updates by phase

VTP Euphoria Phase 1 (P52100031691)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%13%583
100%88%11%580
100%38%11%558
100%13%0%558
100%0%0%558

"—" means MahaRERA shows no figure for that update.

VTP Euphoria Phase 2 (P52100045848)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%98%13%357
100%86%11%355
100%28%11%294
100%17%0%294
100%0%0%294

"—" means MahaRERA shows no figure for that update.

VTP Euphoria Phase 3 (P52100047312)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%13%672
100%90%11%663
100%36%11%206
100%17%0%206
100%0%0%206

"—" means MahaRERA shows no figure for that update.

VTP Euphoria Phase 4 (P52100049849)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%14%196
100%100%11%159
100%53%11%89
100%27%0%89
100%0%0%151

"—" means MahaRERA shows no figure for that update.

VTP Euphoria Phase 5 (P52100077637)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%57%11%64
100%10%11%27
0%0%0%—

"—" means MahaRERA shows no figure for that update.

How to read construction stages
Early stage
The concrete structure (RCC) has not started yet.
Mid-construction
The concrete structure (RCC) is being built.
Nearing possession
The concrete structure (RCC) is complete and final finishes are below 90%.
Ready to move
MahaRERA shows the project Completed, or the concrete structure (RCC) is complete and final finishes are 90% or more.
Concrete structure (RCC)
The reinforced-concrete frame of the building: columns, beams and slabs.
Final finishes
Lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
Lapsed
MahaRERA status when the possession date has passed with no extension or completion filed; it does not by itself mean work has stopped.

How to read construction stages

About this project

VTP Euphoria is a project by Ashdan Developers Private Limited in Manjari Khurd, Pune 412307, registered with MahaRERA as 5 phases (P52100031691, P52100045848, P52100047312, P52100049849, P52100077637). The first phase was launched in November 2021. Together the phases have 2,092 units in 10 buildings, with 1, 2 & 3 BHK homes as registered with MahaRERA. All 5 phases are active on MahaRERA.

The phases' registered possession dates run from December 2026 to December 2028; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 96% complete and final finishes 13% complete. 3 of the 5 phases have their structure complete.

1,872 of the 2,039 units reported for sale are booked (92%). In 2026 registered sales, 80% of flats here sold at ₹11,700 per sq ft or less (up 4% on 2025), counting balconies and terrace in the size. Buyers here paid a rate similar to the typical Manjari Khurd rate in 2026. Most buyers paid ₹42–48 lakh for 1 RK / 1 BHK flats of about 460 sq ft (2024 sales); ₹80 lakh–₹1.00 crore for 2 BHK flats of about 650–860 sq ft (2026 sales); ₹1.34–1.47 crore for 3 BHK flats of about 1,150–1,240 sq ft (2026 sales); ₹1.17–1.48 crore for 4 BHK flats of about 1,450–2,050 sq ft (2023 sales). The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.

VTP's track record in Pune

MahaRERA projects registered 2017–2026 in Pune & PCMC

Projects registered with MahaRERA70
Completed without extending the possession date26
Completed after an extension3
Lapsed10
Under construction31
Possession date extended on the builder's application10
Typical time from launch to 100% structure4 years 11 months
MahaRERA complaints (filed by or against the builder), all VTP projects656 (60 of 70 projects)

See all VTP projects →

Source: MahaRERA registrations P52100031691, P52100045848, P52100047312, P52100049849 and P52100077637.Open MahaRERA and search P52100031691All projects in Manjari, Shewalewadi