VTP projects in Pune
Every MahaRERA project by VTP in the 59 areas FlatNama covers, registered 2017–2026.
- Registered
- 702017–2026
- Under construction
- 31
- Completed
- 2926 without extending
- Complaints
- 656across 60 of 70
Track record
MahaRERA projects registered 2017–2026, in the 59 areas FlatNama covers
| Projects registered with MahaRERA | 70 |
|---|---|
| Completed without extending the possession date | 26 |
| Completed after an extension, or lapsed | 13 |
| Under construction | 31 |
| Possession date extended by the builder | 10 |
| Typical time from launch to 100% structure | 4 years 11 months |
| Complaints on MahaRERA, all VTP projects | 656 (60 of 70 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not extend its possession date. MahaRERA's COVID extensions (6 + 6 months, 2020–21) are not counted as the builder's.
- Completed after an extension, or lapsed: every other registration that is not under construction.
- Under construction: MahaRERA status Active.
- Possession date extended by the builder: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure reached 100% between December 2023 and July 2026, counted from registration.
- Complaints: complaints on MahaRERA filed by or against the builder, on all its projects.
Where they build: Manjari Khurd (16) · Hinjewadi (7) · Mahalunge (6) · Wagholi (4) · Sus (4) · Thergaon (2) · Pashan (1) · Bavdhan Khurd (1) · Manjari (1) · Talegaon Dabhade (1)
Under construction (31)
| Project | Village | Stage | Possession | Booked |
|---|---|---|---|---|
| Altamira by VTP Luxe Phase 1 | Wagholi | Early stage | July 2030 | 338 of 479 booked (71%) |
| Cielo by VTP Luxe | Bavdhan Khurd | Early stage | December 2028 | 276 of 530 booked (52%) |
| Earth 1 by VTP Luxe Phase 1 | Mahalunge | Mid-construction | December 2027 | 848 of 980 booked (87%) |
| Earth 1 by VTP Luxe Phase 2 | Mahalunge | Mid-construction | October 2028 | 247 of 280 booked (88%) |
| Earth 1 by VTP Luxe Phase 3 | Mahalunge | Mid-construction | April 2029 | 214 of 420 booked (51%) |
| Flamante by VTP Luxe Phase 1 | Wagholi | Mid-construction | March 2028 | 625 of 660 booked (95%) |
| Flamante by VTP Luxe Phase 2 | Wagholi | Mid-construction | June 2029 | 363 of 396 booked (92%) |
| Monarque by VTP Luxe Phase 2 | Hinjewadi | Early stage | December 2029 | 34 of 144 booked (24%) |
| Monarque by VTP Luxe Phase 3 | Hinjewadi | Early stage | December 2030 | 109 of 438 booked (25%) |
| Urban Life Phase 1 | Talegaon Dabhade | Mid-construction | December 2022 | 208 of 343 booked (61%) |
| Velvet Villas Phase 1 | Manjari Khurd | Mid-construction | December 2026 | 19 of 31 booked (61%) |
| Velvet Villas Phase 2 | Manjari Khurd | Nearing possession | December 2026 | 7 of 12 booked (58%) |
| VTP Aurelia Phase 1 | Manjari Khurd | Early stage | September 2030 | 376 of 901 booked (42%) |
| VTP Bellissimo Phase 1 | Hinjewadi | Mid-construction | December 2026 | 1,191 of 1,246 booked (96%) |
| VTP Bellissimo Phase 2 | Hinjewadi | Mid-construction | December 2027 | 135 of 156 booked (87%) |
| VTP Bellissimo Phase 3 | Hinjewadi | Mid-construction | March 2027 | 143 of 208 booked (69%) |
| VTP Cielo MHADA | Bavdhan Budruk | Early stage | December 2029 | |
| VTP DOLCE VITA Phase 1 | Manjari Khurd | Mid-construction | December 2028 | 668 of 736 booked (91%) |
| VTP Dolce Vita Phase 2 | Manjari Khurd | Mid-construction | June 2029 | 234 of 343 booked (68%) |
| VTP Dolce Vita Phase 3 | Manjari Khurd | Mid-construction | June 2029 | 368 of 484 booked (76%) |
| VTP Dolce Vita Phase 4 | Manjari Khurd | Mid-construction | June 2029 | 99 of 204 booked (49%) |
| VTP Euphoria Phase 1 | Manjari Khurd | Nearing possession | December 2026 | 583 of 594 booked (98%) |
| VTP Euphoria Phase 2 | Manjari Khurd | Mid-construction | June 2027 | 357 of 360 booked (99%) |
| VTP Euphoria Phase 3 | Manjari Khurd | Nearing possession | March 2028 | 672 of 718 booked (94%) |
| VTP Euphoria Phase 4 | Manjari Khurd | Nearing possession | March 2028 | 196 of 240 booked (82%) |
| VTP Euphoria Phase 5 | Manjari Khurd | Mid-construction | December 2028 | 64 of 180 booked (36%) |
| VTP Monarque Phase 1 | Hinjewadi | Early stage | December 2029 | 285 of 504 booked (57%) |
| VTP Sierra Phase 3 | Sus | Mid-construction | June 2029 | 127 of 152 booked (84%) |
| VTP Sierra PHASE-2 | Sus | Nearing possession | December 2026 | 354 of 361 booked (98%) |
| VTP Verve | Sus | Mid-construction | December 2029 | 644 of 701 booked (92%) |
| VTP Volare | Hinjewadi | Early stage | December 2029 | 477 of 739 booked (65%) |
Completed (29)
| Project | Village | Stage | Possession | Booked |
|---|---|---|---|---|
| Hi Life | Thergaon | Ready to move | March 2024 | All 465 units booked |
| Hi Life phase 2 | ||||
| hi life phase3 | Thergaon | Ready to move | December 2024 | 188 of 191 booked (98%) |
| Purvanchal Phase1 AB | ||||
| Purvanchal Phase2 C D E | ||||
| Urban Balance | ||||
| Urban Nest Phase1 | ||||
| Urban Rise | ||||
| VTP Alpine | ||||
| VTP Beaumonde Building T3 | Manjari Khurd | Ready to move | June 2025 | 210 of 212 booked (99%) |
| Vtp Beaumonde- Nation R2 Tower5 | ||||
| VTP Beaumonde-Nation R2 T1 | ||||
| VTP Beaumonde-Nation R2 Tower4 | ||||
| VTP Belair B And D Building | ||||
| VTP Belair C building | ||||
| VTP Cygnus Building T10 | Manjari Khurd | Ready to move | June 2025 | 152 of 158 booked (96%) |
| VTP Cygnus Building T11 | Manjari Khurd | Ready to move | June 2025 | 211 of 212 booked (100%) |
| VTP Cygnus BuildingT12 and Commercial | Manjari | Ready to move | June 2025 | 185 of 233 booked (79%) |
| Vtp Cygnus- Nation R1-Tower 8 | ||||
| Vtp Cygnus- Nation R1-Tower7 | ||||
| VTP Leonara A and D Building | ||||
| VTP Leonara Building B | ||||
| VTP Leonara building C and F | ||||
| VTP Leonara E Buidling | ||||
| VTP Leonara H building | Mahalunge | Ready to move | December 2023 | 262 of 264 booked (99%) |
| VTP One | ||||
| VTPBelair A Building | ||||
| VTPBelair E and F Building | ||||
| VTPSolitaire Building C AND D | Pashan | Ready to move | June 2024 | All 111 units booked |
Lapsed (10)
| Project | Village | Stage | Possession | Booked |
|---|---|---|---|---|
| Purvanchal F Building | ||||
| VTP Aethereus phase2 | Mahalunge | Finishing stage | December 2025 | 473 of 476 booked (99%) |
| VTP Aethereus- Phase1 | Mahalunge | Finishing stage | June 2026 | 715 of 718 booked (100%) |
| VTP Altair | Wagholi | Nearing possession | June 2026 | 488 of 495 booked (99%) |
| VTP Beaumonde Building T2 | Manjari Khurd | Nearing possession | June 2025 | 263 of 266 booked (99%) |
| VTP Beaumonde Nation R2 Tower6 | ||||
| Vtp Cygnus- Nation R1-Tower 9 | ||||
| VTP Leonara Building G | ||||
| VTP Sierra Phase1 | Sus | Mid-construction | June 2026 | 505 of 515 booked (98%) |
| VTP Solitaire Phase 1 AB |